← Library
Madras High CourtWP/14140/2024allowed

R.Sarada v. The Commissioner Of Survey And Settlement

2024-05-24Honourable Mr Justice G.R.Swaminathan7 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 24.05.2024

CORAM

THE HON'BLE MR.JUSTICE G.R.SWAMINATHAN R.Sarada : Petitioner versus

1. The Commissioner of Survey and Settlement, Directorate of Survey and Settlement, Central Survey Office, Survey House, PWD Estate, Triplicane, Chepauk, Chennai - 600005.

2. The District Collector, Thiruvallur, Tiruvallur Collector Office Complex, Tiruvallur - 602001

3. The Assistant Director, Survey of Land Records, Tiruvallur Collector Office Complex, Tiruvallur - 602001

4. The Inspect of Survey, Survey of Land Records, Tiruvallur Collector Office Complex, Tiruvallur - 602001

5. The Deputy Inspector of Survey,

Survey of Land Records, Tiruvallur Collector Office Complex, Tiruvallur - 602001.

6. The Tahsildar, Poonamalle Taluk Office, Chennai - 600056.

: Respondents Prayer: Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Mandamus directing the respondents herein to conduct a joint Survey in respect of the lands comprised in S.No.82, 81 and 80, situate at Noombal Village, Poonamallee Taluk, Thiruvallur District, after issuing notice to all interested parties.

For Petitioner :

MS.Dipthi Munoth. A For Respondents :

Mr.U.Baranidharan Addl. Govt. Pleader for R.1 to R.6.

ORDER

The petitioner has applied to the jurisdictional authority for conducting joint survey of the petition mentioned lands after issuing notice to all the interested parties. Since the authority had not acted upon the petitioner's request, this writ petition came to be filed.

2.This writ petition is disposed of at the admission stage itself. It is open to any aggrieved party to move this Court either by way of review or recall of this order, if there is any suppression of material facts by the petitioner.

3.The Writ Petition is disposed of with the following directions:- (I) The petitioner is directed to submit his / her application in on-line mode. The survey authority will scrutinize if the application submitted by the petitioner is in order. (II) The petitioner will have to enclose all the relevant documents such as patta. The applicant must have individual patta in his / her name. If he / she is having joint patta, copattadars must give their consent for conducting survey. (III) The survey authority will issue notice to the writ petitioner as well as the adjacent land owners and also to the interested persons, if any.

(IV) Enquiry shall be held. During enquiry, objections raised by the adjacent land owners / interested persons shall be

considered.

(V) If according to the jurisdictional authority, the objections are without any basis, the same shall be overruled and the objectors shall be informed accordingly. But the survey will be conducted only after a period of six weeks so that the objector can move the concerned Court for injunction. If before the proposed date of survey, the objector is unable to obtain any injunction order, the survey can very well go on. (VI) It is open to the parties to serve memo of instructions to the surveyor at the time of conducting survey. The same will be borne in mind. While it cannot be binding on the surveyor, the same will be taken note of.

(VII) If the jurisdictional authority finds objections to be having substance, then, he shall call upon the applicant to move the jurisdictional civil Court for agitating his rights. (VIII) If required, the survey authority is empowered to seek aid of the jurisdictional police and the jurisdictional police are mandated to grant police protection.

(IX) It is made clear that at the end of the survey exercise, survey stones alone can be installed. The exercise of survey and demarcation undertaken pursuant to the direction of this Court can never result in dispossession of any party. If the petitioner wants to put up fencing and if there is any objection from any private party, fencing can be put up only after the petitioner obtains decree from the jurisdictional Civil Court.

(X) The survey authority will conclude the entire exercise one way or the other within a period of three months after service of notice on the interested persons.

(XI) A copy of the survey report along with sketch will be served on the parties. No costs.

24.05.2024 Index : Yes/No : Yes/No shr To

1. The Commissioner of Survey and Settlement, Directorate of Survey and Settlement, Central Survey Office, Survey House, PWD Estate, Triplicane, Chepauk, Chennai - 600005.

2. The District Collector, Thiruvallur, Tiruvallur Collector Office Complex, Tiruvallur - 602001.

3. The Assistant Director , Survey of Land Records, Tiruvallur Collector Office Complex, Tiruvallur - 602001.

4. The Inspect of Survey, Survey of Land Records, Tiruvallur Collector Office Complex, Tiruvallur - 602001.

5. The Deputy Inspector of Survey, Survey of Land Records, Tiruvallur Collector Office Complex, Tiruvallur - 602001.

6. The Tahsildar, Poonamalle Taluk Office, Chennai - 600056.

G.R.SWAMINATHAN, J.

(shr) 24.05.2024