Mrs.Chandrakala Jaiswal v. M/S.Ebc Moscow Ltd.,
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 19.12.2013
CORAM
THE HON'BLE MR.JUSTICE M.JAICHANDREN C.S.No.1091 of 2008 MRS.CHANDRAKALA JAISWAL [ PLAINTIFF ] SOLE PROPRIETOR M/S.C.K.BEARING COMPANY AMAR COMPLEX NO.276 OLD NO.196 THAMBU CHETTY CHENNAI - 1 REP BY HER SON AND POWER OF ATTORNEY AGENT MR.RAVI JAISWAL Vs 1 M/S.EBC MOSCOW LTD.
6 NOVCOSGTAPOVSKAYA STR MOSCOW - 116088.
2 M/S.EPK BEARINGS INDIA PVT LTD PLOT NO.4B, IDA, CHERLAPALLY PHASE-III, RANGA REDDY DISTRICT HYDRABAD - 500 051 ANDHRA PRADESH 3 M/S.EPC BEARINGS (INDIA) PVT LTD PLOT NO.131/C ROAD NO.15 IDA MALLAPUR HYDRABAD - 600 076 ANDHRAPRADESH [ DEFENDANTS] This Civil Suit has been filed to pass a Judgment and Decree:
(a) Directing the defendants jointly and severally to pay a sum of Rs.35,74,562/- together with interest at the rate of 12% per annum on the sum of Rs.33,59,205/- from the date of the plaint until realization.
(b) to pay the cost of the suit.
For petitioner Mr.S.Thanka Sivan For respondents : Mr.Kasturi Rangan for Mr.Sampath Kumar and Associates for D1 and D2 Mr.B.T.Seshadri for R4
O R D E R
This Civil Suit was referred for mediation to the Tamil Nadu Mediation and Conciliation Centre, High Court of Madras, by the order of this Court, dated 12.7.2013.
2. A communication, dated 18.11.2013, of the Tamil Nadu Mediation and Conciliation Centre, High Court of Madras, enclosing a copy of its Mediation Report, dated 28.10.2013, has been received, and in the said Mediation Report, it is stated as follows:- "Plaintiff and the Defendants are arrived at an amicable settlement and have filed the Joint Memo of Compromise. Hence the matter is sent back to the Hon'ble Court."
3. As the parties have arrived at a settlement in terms of the Joint Memo of Compromise, dated 26.10.2013, this civil suit is listed for passing orders in terms of the said Joint Memo of Compromise.
4. The Joint Memo of Compromise, dated 26.10.2013,
signed by the parties and the counsels appearing for the parties concerned, reads as follows:- "Joint Memo of Compromise filed by the plaintiff and the defendants is as follows:
The parties above named submit as follows:
The plaintiff has filed the above suit seeking recovery of a sum of Rs.34,72,562/- together with further interest from the defendants. During the pendency of the above suit, the matter was referred to mediation before the Tamil Nadu Mediation & Conciliation Centre. Pending mediation, the second defendant which is a 100% subsidiary of the first defendant offered on behalf of the first defendant and on its own behalf to settle the plaintiff's claim by paying a consolidated sum of Rs.6,00,000/- (Rupees six lakhs only) towards full and final settlement of the entire suit claim and the said offer has been accepted by the plaintiff with the view of amicably settling the dispute. The plaintiff also indemnify the defendants that they will not make any claim on the matters raised in the suit in future.
In furtherance to the above, the second defendant on behalf of their Hoding Company and on their behalf has paid the said sum of Rs.6,00,000/- (Rupees six lakhs only) by way of Demand Draft bearing No.511268 dated 25.10.2013 drawn on Syndicate Bank, Hyderabad. The said sum has been received by the plaintiff in full and final settlement of all his claim in the above
suit.
Hence it is prayed that full and final settlement may be recorded in the above suit and the suit may be dismissed as settled out of Court. It is also prayed that this Hon'ble Court may be pleased to order refund of 50% court fee paid by the plaintiff and thus render justice."
5. In terms of the settlement arrived at between the parties, which is recorded under the Joint Memo of Compromise, dated 26.10.2013, and in terms of the Mediation Report, dated 28.10.2013, before the Tamil Nadu Mediation and Conciliation Centre, High Court of Madras, this suit is decreed, recording the terms of the Joint Memo of Compromise, dated 26.10.2013. The terms of the Joint Memo of Compromise, dated 26.10.2013 and the Mediation Report, dated 28.10.2013, of the Mediation Centre, shall form part of the order. Connected Applications Nos.989 and 990 of 2009 and Applications Nos.5424 and 5425 of 2008 are closed. sd/.M.J.J 19.12.2013 //Certified to be a true copy// Dated this the day of 2015 R.s/28.07.2015 COURT OFFICER From 25.09.2008 the Registry is issuing certified copies of the Order/Judgment Decree in this format.