M/S.Venus Electrical Works v. Assistatnt General Manager
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 18.06.2026
CORAM
THE HON'BLE MR.SUSHRUT ARVIND DHARMADHIKARI, CHIEF JUSTICE AND THE HON'BLE MR.JUSTICE G.ARUL MURUGAN and WMP Nos.21063 and 28024 of 2022 M/s.Venus Electrical Works Rep. By its Partner A.Murugavel S-9, 2nd Floor, New Shopping Complex, No.100, Jawaharlal Nehru Street, Puducherry - 605 001.
.. Petitioner -vsAssistant General Manager, Punjab National Bank, Circle SASTRA Centre, Chennai South, No.46-49, Mezzanine Floor, PNB Towers, Royapettah High Road, Chennai 600 014.
.. Respondent Prayer: Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Mandamus to direct the respondents to grant additional time of 90 days to make the balance payment of Rs.71,32,000/- as one time settlement.
For Petitioner :
No appearance For Respondent :
Mr.M.L.Ganesh
ORDER
(Order of the Court was made by the Hon'ble Chief Justice) No one appears for the petitioner.
2. From the prayer clause, it is seen that a direction has been sought to make the balance payment in additional time of 90 days.
3. Learned counsel for the respondent submitted that the property has already been auctioned and the sale certificate has also been issued.
In view of the aforesaid, no relief can be granted. Accordingly, this writ petition is dismissed. There shall be no order as to costs. Consequently, the interim applications stand closed. (SUSHRUT ARVIND DHARMADHIKARI, CJ.) (G.ARUL MURUGAN, J.) 18.06.2026 Index : Yes/No : Yes/No sra
To The Assistant General Manager, Punjab National Bank, Circle SASTRA Centre, Chennai South, No.46-49, Mezzanine Floor, PNB Towers, Royapettah High Road, Chennai 600 014.
THE HON'BLE CHIEF JUSTICE AND G.ARUL MURUGAN, J.
(sra) 18.06.2026