Syed Sadiq Mosque & Dargah, v. The Chairman,
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 08.11.2017
CORAM
THE HONOURABLE MR.JUSTICE RAVICHANDRABAABU W.P.No.28546 of 2017 Syed Sadiq Mosque & Dargah rep. by its President and Muthavalli Mr.Z.Jamaludeen,Kundrathur Main Road, Mangadu Village, Chennai - 600 122.
..Petitioner vs.
1. The Chairman, Tamil Nadu Electricity Board, No.144, Anna Salai, Chennai - 600 002.
2. The Assistant Divisional Engineer, Tamil Nadu Electricity Board / TANGEDCO (Mangadu), Chettiyaragaram, Porur, Chennai - 600 116.
3. The Assistant Engineer, Tamil Nadu Electricity Board / TANGEDCO, Mangadu, Chennai - 600 122.
... Respondents Writ Petition filed under Article 226 of the Constitution of India praying for the issuance of a Writ of Mandamus to direct the 3rd respondent to consider the petitioner application dated 25.08.2017 requesting to provide electricity connection to the Wakf property, viz., newly constructed building and shops in Dargah Complex, Kundrathur Main Road, Mangadu, Chennai - 600122.
For Petitioner : Mr.T.Velumani For Respondents : Mr.S.K.Rameshwar, Standing counsel for R1 to R3.
O R D E R
Mr.S.K.Rameshwar, learned Standing counsel takes notice for the respondents. By consent of the parties, the writ petition itself is taken up for final disposal.
2. The petitioner seeks for a mandamus to direct the 3rd respondent to consider their application dated 25.08.2017, wherein and whereby, they sought to provide electricity connection to the Wakf property, viz., newly constructed building and shops in Dargah Complex, Kundrathur Main Road, Mangadu, Chennai - 600122.
3. The grievance of the petitioner is that the respondents are not considering the said request so far.
4. Therefore, this writ petition is disposed of only with a direction to the 3rd respondent to consider the request of the petitioner and pass appropriate orders on merits and in accordance with law, after providing opportunity of hearing to the petitioner and other affected parties, if any. Such exercise shall be done by the 3rd respondent within a period of four weeks form the date of receipt of a copy of this order. No costs. Sd/- Asst.Registrar (CS IV ) /true copy/ Sub Asst. Registrar vsi To
1. The Chairman, Tamil Nadu Electricity Board, No.144, Anna Salai, Chennai - 600 002.
2. The Assistant Divisional Engineer, Tamil Nadu Electricity Board / TANGEDCO (Mangadu), Chettiyaragaram, Porur, Chennai - 600 116.
3. The Assistant Engineer, Tamil Nadu electricity Board / TANGEDCO, Mangadu, Chennai - 600 122.
+ 1 cc to Mr.T.Velumani Advocate,SR.79536 + 1 cc to Mr.S.K.Rameshwar, Advocate,SR.79082 W.P.No.28546 of 2017 GJII(CO) NR 30/11/2017