Sri Masadachi Amman Construction v. The Engineer In Chief
2024:MHC:5980
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 29-01-2024
CORAM
THE HONOURABLE MR.JUSTICE S.M. SUBRAMANIAM And WMP Nos.18207 and 18209 of 2020 Sri Masadachi Amman Construction, Represented by its Managing Partner R.Sundaram, (Male/52 years0, 3/1-F, Santhaipettai, Singalanthapuram Post, Rasipuram Taluk, Namakkal District.
.. Petitioner -vs1.The Engineer-in-Chief Engineer (Buildings), 2.The Engineer-in-Chief Water Resources Department (WRD),
Chief Engineer (General), 3.The Chief Engineer, Public Works Department (Buildings), Chengulam Colony, Circuit House, Trichy Region, Trichy-20.
4.The Superintending Engineer, Building (Construction and Maintenance) Circle, P.B.No.724, Kumarasamipatti Post, Salem-636 007.
.. Respondents Writ Petition is filed under Article 226 of the Constitution of India praying for the issuance of a Writ of Certiorarified Mandamus, calling for the records from the fourth respondent issued Retender Notice (second call) No.11/2020-21/SE/B (C&M) C/Sim dated 08.09.2020 for Package-I and another Retender Notice (second call) No.11/2020-21/SE/B (C&M) C/Sim dated 08.09.2020 for Package-II, to quash the same and consequently direct the fourth respondent to issue afresh tender in the light of the G.O.Ms.No.471, Finance (Salaries) Department, dated 30.09.2007. For Petitioner :
Mr.I.Abrar Md Abdullah
For Respondents :
Mr.G.Ameedius, Government Advocate.
O R D E R
The learned Government Advocate, appearing on behalf of the respondents, made a submission that Tender Notification is under challenge in the present writ petition and during the pendency of the present writ petition, the tender job was completed in all respects. Therefore, the cause aroused for the purpose of filing the present writ petition did not exist as of now.
2. Accordingly, the present writ petition stands disposed of as infructuous. However, there shall be no order as to costs. Consequently, the connected miscellaneous petitions are closed. 29-01-2024 Index : Yes/No Internet: Yes/No Speaking order/Non-Speaking order Svn
To 1.The Engineer-in-Chief Engineer (Buildings), 2.The Engineer-in-Chief Water Resources Department (WRD), Chief Engineer (General), 3.The Chief Engineer, Public Works Department (Buildings), Chengulam Colony, Circuit House, Trichy Region, Trichy-20.
4.The Superintending Engineer, Building (Construction and Maintenance) Circle, P.B.No.724, Kumarasamipatti Post, Salem-636 007.
S.M.SUBRAMANIAM, J.
Svn WP 14649 of 2020 29-01-2024