M/S.Sowmiya Spinners Pvt.Ltd., v. The Chairman,
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 13.06.2018
CORAM
THE HONOURABLE MR.JUSTICE T.RAJA W.P.No.14263 of 2018 M/s Sowmiya Spinners Pvt.Ltd., HTSC No.400 No.535/2A, 2B, 525/1B, K.G.Palayam Village Kariyampalayam, Annur 641 653 Coimbatore rep.by its Authorized Signatory P.Mohan Raj ..
Petitioner -vs1. The Chairman Tamil Nadu Generation and Distribution Corporation Limited 144, Anna Salai Chennai 600 002
2. The Superintending Engineer Coimbatore North Electricity Distribution Circle Tamil Nadu Generation and Distribution Corporation Limited, Tatabad Coimbatore ..
Respondents Petition under Article 226 of the Constitution of India, praying for the issue of a Writ of Mandamus, directing the second respondent to permit the petitioner to pay Rs.17,63,274/- alone towards the Additional Security Deposit in 5 equal monthly installments along with the regular current consumption charges. For Petitioner ::
Mr.R.S.Pandiyaraj For Respondents ::
Mr.S.K.Rameshuwar Standing Counsel
ORDER
The petitioner is manufacturing yarn products and giving employment opportunities to several hundreds of rural people and they are having HT service connection bearing No.400 under the jurisdiction of the second respondent herein. They have been already maintaining the Current Consumption Deposit of Rs.28,35,709/-. As per Regulation 5(5)(ii)(a) of the Tamil Nadu Electricity Supply Code 2004, the Current Consumption Deposit should be two times of the average electricity charges for the preceding 12 months prior to April for the monthly billed consumers like the petitioner. While so, the second respondent has sought for payment of Additional Current Consumption Deposit of Rs.26,44,911/- over and above the existing deposit of Rs.28,35,709/- in a lump sum from the petitioner, failing which to face disconnection. When the proceeding dated 26.
4.2018 was issued by the Superintending Engineer, Coimbatore Electricity Distribution Circle/North to the petitioner claiming Rs.26,44,911/-, they have permitted the petitioner to pay the said deposit in three equated monthly installments on 19.5.2018, 19.6.2018 & 19.7.2018. Accordingly, the petitioner has also paid the first installment. Since this Court, while considering a similar prayer in W.P.No.10773 of 2018 by order dated 26.4.2018, has permitted the petitioner therein to pay the Additional Current Consumption Deposit in six installments, the learned counsel sought for a similar benefit to be extended to the petitioner in this case also for payment of the balance sum of Rs.17,63,274/- in five equated monthly installments.
2. Mr.S.K.Rameshuwar, learned standing counsel for the respondents submitted that after the petitioner approached the respondents expressing their difficulty in paying the Additional Current Consumption Deposit of Rs.26,44,911/- over and above the existing deposit, as per the Regulation 5(5)(ii)(a) of the Tamil Nadu Electricity Supply Code 2004, considering the difficulty faced by them, they were permitted to pay the Additional Current Consumption Deposit in three installments as mentioned in the proceeding dated 26.4.2018. However, after making the first installment, they have come to this Court.
3. It is true that the petitioner was permitted to pay the Additional Current Consumption Deposit of Rs.26,44,911/- in three installments and out of the three installments, the petitioner had also paid the first installment on 19.5.2018. When this Court in similar circumstances had permitted the industries like the petitioner to pay the Additional Current Consumption Deposit in six installments, following the order passed in W.P.No.10773 of 2018 dated 26.4.2018, this Court directs the petitioner herein to deposit the balance Additional Current Consumption Deposit of Rs.17,63,274/- in five equated
installments on 19.6.2018, 19.7.2018, 19.8.2018, 19.9.2018 & 19.10.2018, apart from the regular current consumption charges. It is made clear that if the petitioner commits any default in making the deposit, the respondents are at liberty to take appropriate action in accordance with law. With this direction, the writ petition stands disposed of. No costs. Sd/- Assistant Registrar(CS IX) //True Copy// Sub Assistant Registrar ss To
1. The Chairman Tamil Nadu Generation and Distribution Corporation Limited 144, Anna Salai Chennai 600 002
2. The Superintending Engineer Coimbatore North Electricity Distribution Circle Tamil Nadu Generation and Distribution Corporation Limited, Tatabad Coimbatore +1cc to Mr.R.S.Pandiyaraj, Advocate Sr.No.37220 sm:19.6.2018 W.P.No.14263 of 2018 2/2