Arunachalam Projects And Infrastructure Pvt Ltd v. E Mohan
A No. 2573 of 2026
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 25-06-2026
CORAM
THE HON'BLE MR.JUSTICE K.KUMARESH BABU A No. 2573 of 2026 M/s.Arunachalam Projects And Infrastructure Pvt Ltd Rep.by V.Partasarathy, Arunachala Building 2nd Floor, No. 107/76, Avvai Shanmugam Salai (Llyods road) Royapettah, Chennai, Tamil Nadu- 600014 ..Applicant(s) Vs Mr.E.Mohan Rep.of M/s.Sri Krishna Lorry Service, (Also known as M/s.SKLS Lorry Service) Survey No.93/1c/2b, GNT Road, Redhills, Chennai - 600052.
..Respondent(s) Judges Summons under Order XIV Rule 1 of Madras High Court Original Side Rules read with Section 29A (5) of the Arbitration and Conciliation Act, 1996, pleased to Extend the time for completion of arbitration proceedings by a period of 4 months.
For Applicant(s):
Mr.AK Mylsamy For Respondent(s):
Mr.S.Kamalesh Kannan
ORDER
The present application had been taken out by the applicant herein to seek extension of mandate for a further period of four (4) months. __________ https://www.mhc.tn.gov.in/judis
A No. 2573 of 2026 K.KUMARESH BABU, J.
2. Mr.S.Kamalesh Kannan, learned counsel, accepts notice for the respondent and has no objection to extend the mandate.
3. Considering the stage on which the arbitral proceedings are at, this Court is inclined to extend the mandate for a further period of four (4) months from the date of receipt of a copy of this order. The learned Arbitrator is requested to complete the proceedings and pass an Award within the said period of four (4) months and the respective parties are also directed to co-operate with the learned Arbitrator.
4. This application is disposed of in the above terms. 25-06-2026 Index: Yes/No Speaking/Non-speaking order kak A No. 2573 of 2026 __________ https://www.mhc.tn.gov.in/judis