Madras High CourtWP/8808/2014settled before the lokadalats

The Divisional Railway Manager v. The Presiding Officer

2024-09-14Honourable Mr.Justice K.Gnanaprakasam (Retd.)5 pages

HIGH COURT LEGAL SERVICES COMMITTEE, CHENNAI National Lok Adalat organised by the High Court Legal Services Committee Saturday the 14th day of September 2024 NATIONAL LOK ADALAT AWARD (Chapter VI and u/s 21 of Legal Services Authorities Act, 1987) Presided over by THE HONOURABLE Mr.JUSTICE K. GNANAPRAKASAM (RETD.) and Members:

1.Mr.S. Baskaran (Retd., DJ) 2.Ms.Jemmy Vasanth W.P. Nos. 8808 of 2014 & 32421 of 2015 and W.M.P.Nos. 1 of 2015 & 111 of 2022 (Writ Petitions are filed under Article 226 of the Constitution of India to issue a writ of certiorari, to call for the records on the file of the first respondent made in C.P. No.2 of 2013 and C.P. No. 8 of 2014 dated 25.06.2015 and quash the same) The Divisional Railway Manager/Personnel/MAS, Divisional Office, Park Town, Chennai - 600 003.

... Petitioner in both W.Ps Vs.

1.The Presiding Officer, The Central Government Industrial Tribunal cum Labour Court, Chennai - 600 006.

2.K. Kuppan ... Respondents

in both W.Ps With the consent of both the parties, these cases are taken up for settlement before this Lok Adalat. Both the parties are present. Mrs. T.P.Savitha, learned counsel for the petitioner and Mr.G.Muthu, learned counsel for the second respondent are present. After mutual discussion, negotiation, mediation and conciliation between both parties, they arrived at a compromise to settle the matter as follows:

TERMS OF SETTLEMENT This Writ Petition has been filed to call for the records on the file of the first respondent made in C.P. No.2 of 2013 and C.P. No. 8 of 2014 respectively dated 25.06.2015 and quash the same.

2. After due deliberation and consultation, both the parties have now agreed to resolve the issue by paying a sum of Rs.6,85,122/- only after having paid the other amounts, which the second respondent agrees and admits. The second respondent has no other claim against the appellant. Now the petitioner has agreed to pay a sum of Rs.6,85,122/- as full and final settlement to the second respondent. The writ petitioner is directed to deposit the award amount within eight weeks from the date of receipt of copy of this order, in the account of the second respondent i.e., Account No. 6100479449, IFSC Code: IDIB000K002, Indian Bank, Kadambattur (305) Branch, as agreed by the writ petitioner. Accordingly, the matter is settled amicably between the parties. In view of the same, nothing remains for further adjudication in the writ petitions.

3. Recording the above statement made by the parties as well as by the learned counsel appearing on either side, these writ petitions stands disposed of. No costs. Consequently, the connected Miscellaneous Petitions are closed.

The Divisional Railway Manager/Personnel/MAS, Divisional Office, Park Town, Chennai - 600 003.

Counsel for Petitioner K. Kuppan Counsel for Second Respondent This Lok Adalat award is passed in terms of the above settlement. The full Court fee paid shall be refunded to the appellant in the manner provided under Section 69-A of the Tamil Nadu Court-Fees and Suits Valuation Act, 1955 and the Court Fees Act, 1870 as provided for under sub Sec.1 of Section 21 r/w 25 of LSA Act 1987 as amended in 1994. Judge Member Member To: The parties/Advocate concerned

Copy to:

1.The Presiding Officer, The Central Government Industrial Tribunal cum Labour Court, Chennai - 600 006.

2.The Secretary, High Court Legal Services Committee, Chennai. 3.The Section Officer, V.R.Section, High Court, Madras. 4.The Section Officer, Lok Adalat Section, High Court, Madras.+2 copies at/ham

K. GNANAPRAKASAM, J. (RETD.) at/ham W.P. Nos. 8808 of 2014 & 32421 of 2015 and W.M.P.Nos. 1 of 2015 & 111 of 2022 14.09.2024