R.Santhosam v. Er.M.A. Hellan
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 23.11.2017 CORAM :
THE HON'BLE MR. JUSTICE S.M.SUBRAMANIAM Contempt Petition No.2771 of 2013 in W.P.No.29477 of 2010 R.Santhosam ...
Petitioner Vs.
Er.M.A.Hellan, M.E., The Superintending Engineer, Mettur Electricity Distribution Circle - Tamil Nadu Electricity Board, Now TANGEDCO, Mettur Dam, Pin Code 637 401.
...
Respondent Prayer : Contempt Petition filed under Section 11 of the Contempt of Courts Act, to punish the respondents for willfully disobeying the orders of this Court dated 23.12.2010 in W.P.No.29477 of 2010.
For Petitioner : Mr.S.Elamurugan For Respondent : Mr.P.R.Dhilipkumar
O R D E R
The learned counsel appearing for the petitioner made a submission that during the pendency of the contempt petition the order passed by this Court on 23.12.2010 in https://hcservices.ecourts.gov.in/hcservices/ W.P.No.29477 of 2010, has been implemented.
2. Thus, no further adjudication is required in this contempt petition. Accordingly, the contempt petition stands closed.
SD/- ASSISTANT REGISTRAR(COMM.CASES) ms //Certified to be true copy// Dated at Madras this the day of 2018. COURT OFFICER(O.S.) from 25th day of September 2008 the Registry is issuing Certified copies of the Orders/Judgments/Decrees in this format.
CO/23/01/2018 https://hcservices.ecourts.gov.in/hcservices/