M/S.Concrete Products And v. The Chief Track Engineer
In the High Court of Judicature at Madras Dated : 20.02.2015 Coram :
The Hon'ble Mr.Sanjay Kishan Kaul, Chief Justice O.P.No.654 of 2012 M/s.Concrete Products & Construction Company, rep. By its Joint Managing Partner K.Jacob, No.398, Poonamallee High Road, Kilpauk, Chennai-600 010.
.. Petitioner -vs1.Chief Track Engineer, Southern Railway, Chennai-600 003.
2.The Principal Chief Engineer, Southern Railway, Park Town, Chennai-600 003.
.. Respondents Petition filed under Section 11 (6) of the Arbitration and Conciliation Act, 1996, to appoint a sole Arbitrator to adjudicate and resolve the disputes and differences that have arisen between the petitioner and the respondents in respect of Agreement No.CE/2/CS of 2010 dated 20.02.2010 entered between the petitioner and the respondent. For Petitioner : Mr.A.Jenasenan For Respondents : Mr.V.G.Suresh Kumar * * * * *
O R D E R
Learned counsel for the petitioner submits that the petition has become infructuous, as the award has been passed by the Arbitrator. An endorsement has been made.
2.Original Petition, thus, stands disposed of as infructous. (S.K.K., CJ.) 20.02.2015 sra