← Library
Madras High CourtOP/608/2014dismissed

M/S.Om Spun Pipes And Concrete v. The Union Of India

2019-07-11Honourable Mr Justice N. Sathish Kumar7 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 11.07.2019 CORAM :

THE HONOURABLE MR. JUSTICE N.SATHISH KUMAR O.P.No.608 of 2014 Om Spun Pipes & Concrete Works, PRR Coony, Kavvur, Nellore District (A.P.) - 524 137.

.. Petitioner Vs.

1. The Union of India, Rep. By the General manager, Southern Railway, Chennai.

2. The Senior Divisional Engineer/Co.ord, Southern Railway, Works Branch, Tiruchirapalli.

3. The Divisional Engineer/CTR, Works Branch, Southern Railway, Tiruchirapalli.

4. The Arbitral Tribunal represented by Mr.Lalloo Singh, Chief Administration Officer, North Central Railway Presiding Arbitrator.

5. Mrs..Sujatha Jayaraj, Financial Advisor & Chief Accounts Officer/MAS Southern Railway, Co-Arbitrator, Chennai - 8.

6. Mr.S.G.Jundekeri, Chief Electrical Service Engineer, Southern Railway ICF, Perambur, Chennai - 11. Co-Arbitrator .. Respondents

PRAYER: Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the Award dated 06.02.2014 passed by the fourth respondent in dispute between the petitioner and the respondents 1 to 3 made in Arbitration Dispute, bearing letter No.G.16/DGM/ARB/2011/33, dated 08.09.2011 and thereby, allow the petitioner's claim.

For Petitioner : Mr.D.Padmanabhan for Mr.Francis Xavier For Respondents : Mr.P.T.Ramkumar - R1 to R3

O R D E R

This petition has been filed challenging the Award dated 06.02.2014 passed by the Arbitral Tribunal.

2. Originally, the letter of acceptance was given to the petitioner on 12.10.2007 for construction of 6 subways in various places. The time for completion of work is nine months and the work has to be completed on or before 11.07.2008. The contract also provides that the contractor has to obtain test reports from the Government authorities. As the performance of guarantee has not been executed by the contractor till 14.02.2008, the contract has been fore closed on 19.06.2009. In view of the same, claim has been preferred on various heads as detailed below :

Claim No.

Description of Claim Amount claimed (Rs.) 1.

Idling of labour and machiner awaiting to start the work from 01.12.2007 to 07.04.2009 (493 days) that is till the foreclosure of the work 2,37,40,000/- 2.

The materials were purchased for the work and could not be utilized due to not allowing the work to be executed and some lost in wear and tear and theft and balance resold in market at 50% of cost of materials is claimed 17,17,750/- 3.

Claim for expenditure incurred on test reports which were not finalized (approx.) 60,000/- 4.

Loss of expenditure incurred on establishment of office building, godown for materials, sheds and mess charges 2,00,000/- 5.

Loss o profit at 10% of the agreement value for not allowing the work to be executed.

24,38,522/- 6.

Damages claimed on the expenditure incurred on claim Nos.1, 2, 3 & 4 at 15% p.a. till the date of their payment Not quantified

3. The Arbitral Tribunal has awarded only Rs.15,455/- towards expenditure incurred on test reports which were not finalized and the rest of the claim has been dismissed by the Arbitrators.

4. The learned counsel for the petitioner submitted that Arbitral Tribunal has not appreciated the fact that the respondents 1 to 3 have committed breach of contract by unilaterally terminating the contract without any justifiable reasons and thereby caused, huge loss to the petitioner, who had done all the required

works for commencing the work allotted to the petitioner. The Arbitral Tribunal has not considered the entire evidence and mechanically negatived the claim of the petitioner and the Award has to be set aside.

5. The learned counsel for the respondents 1 to 3 submitted that even after a lapse of five months, the petitioner has not even executed the bank guarantee and has not commenced the work. The Arbitral Tribunal has considered the entire evidence and rightly passed the Award and the same cannot be interfered.

6. Heard the learned counsel appearing for the petitioner and the learned counsel appearing for the respondents and perused the entire materials available on record.

7. The learned Arbitrators have factually found that the vouchers have been created only to show the expenditure incurred by the petitioner. The learned Arbitrators have made threadbare analysis of the entire documents and found that the vouchers have been fabricated only for the purpose of the claim. Therefore, the contention of the learned counsel for the petitioner that the Arbitrator has not considered the entire evidence and mechanically negatived the claim of the petitioner cannot be countenanced.

8. Admittedly, the work has not been commenced by the petitioner even for a single day. Before commencement of work, the contract itself has been foreclosed. These are all matter of evidence and the same is not in dispute. Such being the position, paying huge amount for the labourers and claiming amount under head of idling of labour and machinery is highly improbable. Infact, the learned Arbitrators have taken into account the entire evidence and found that those vouchers have been written by the single handwriting and there is no corresponding entries in the ledgers. When the learned Arbitrators have factually found that the claim of the petitioner has not been proved, this Court cannot re-appreciate the entire evidence as an appellate Court. Hence, I do not find any ground as contemplated under section 34 of the Arbitration and Conciliation Act to interfere with the Award passed by the Arbitral Tribunal.

9. Accordingly, this Original Petition is dismissed. No cost. 11.07.2019 vrc Index : Yes/ No Internet : Yes Speaking/Non-speaking Order

To

1. The Union of India, Rep. By the General manager, Southern Railway, Chennai.

2. The Senior Divisional Engineer/Co.ord, Southern Railway, Works Branch, Tiruchirapalli.

3. The Divisional Engineer/CTR, Works Branch, Southern Railway, Tiruchirapalli.

4. The Arbitral Tribunal Mr.Lalloo Singh, Chief Administration Officer, North Central Railway Presiding Arbitrator.

5. Mrs..Sujatha Jayaraj, Financial Advisor & Chief Accounts Officer/MAS Southern Railway, Co-Arbitrator, Chennai - 8.

6. Mr.S.G.Jundekeri, Chief Electrical Service Engineer, Southern Railway ICF, Perambur, Chennai - 11. Co-Arbitrator

N.SATHISH KUMAR, J.

vrc O.P.No.608 of 2014 11.07.2019