G.Palani v. The Member Secretary
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 27.03.2015
CORAM:
THE HON'BLE MR.JUSTICE SATISH K. AGNIHOTRI AND THE HON'BLE MR.JUSTICE M.VENUGOPAL W.P. No.8837 of 2015 G. Palani
...Petitioner
vs.
The Member Secretary Chennai Metropolitan Development Authority Thala Muthu Natarajar Maligai No.1, Gandhi Irwin Road Egmore, Chennai 600 008 The Commissioner Corporation of Chennai Ripon Building Park Town Chennai 600 003 The Executive Engineer Corporation of Chennai Zone No.IX No.1, Lake Area, IV Cross Street Nungambakkam Chennai 600 034 A.S. Khader Basha M.B. Habeebur Rahman
...Respondents
Writ Petition filed under Article 226 of the Constitution of India seeking a writ of mandamus directing the third respondent to consider the petitioner's representation dated 13.12.2014.
For petitioner :
Mr. K. Murali For R1 :
Mr. K. Raja Shrinivas For RR 2 & 3 :
Mr. G. Anantharangan
ORDER
(Order of the Court was made by SATISH K. AGNIHOTRI, J.) Mr. K. Raja Shrinivas, learned Standing Counsel, takes notice for the first respondent. Mr. G. Anantharangan, learned Standing Counsel, takes notice for respondents 2 and 3. It is not necessary to issue notice to respondents 4 and 5 as it is a case of only consideration of the petitioner's representation and no decision can be taken on the said representation without affording an opportunity of hearing to those respondents. Thus, we are passing this order at the admission stage itself, without issuing notice to the said respondents.
The petitioner, aggrieved by the alleged unauthorised construction put up by the private respondents herein, has submitted a representation dated 13.12.2014 to the third respondent, seeking removal of the said unauthorised construction. Finding no response to the said representation, the petitioner has come up with the instant writ petition seeking a direction to the third respondent to consider and pass orders on his aforestated representation, within a time frame.
Considering the limited nature of the relief sought by the petitioner, we direct the third respondent to consider and pass orders on the petitioner's representation dated 13.12.2014 on its own merits and in accordance with law, within a period of six weeks from the date of receipt of a copy of this order. Needless to state that the alleged encroachers shall be given a due opportunity of hearing before orders are passed on the petitioner's representation. With the above direction and observation, the writ petition stands disposed of. Costs made easy.
Sd/- Assistant Registrar(CS-II) //True Copy// Sub Assistant Registrar
cad To The Member Secretary Chennai Metropolitan Development Authority Thala Muthu Natarajar Maligai No.1, Gandhi Irwin Road Egmore, Chennai 600 008 The Commissioner Corporation of Chennai Ripon Building Park Town Chennai 600 003 The Executive Engineer Corporation of Chennai Zone No.IX No.1, Lake Area, IV Cross Street Nungambakkam Chennai 600 034 1 CC to Mr. K. Murali, Advocate SR.No. 17397 1 CC to Mr. K. Raja Shrinivas, Advocate SR.No. 17713 1 CC to Mr. G. Anantharangan, Advocate SR.No. 17591 W.P. No. 8837 of 2015 VGI (CO) PSI (09.04.2015)