C.M.P. Nos.12591, 12627 and 12921 of 2022 in W.A.SR.Nos. 57792, 57793 & 57800 of 2022 THE HON'BLE ACTING CHIEF JUSTICE and SUNDER MOHAN, J (Order of the Court made by SUNDER MOHAN, J) There is a delay of 3 days in preferring the above Writ Appeals.
2. Mr.J. Rajamuneshwaran, learned counsel takes notice for the 1st respondent and Ms. R.Anitha, learned Special Government Pleader, takes notice for the respondents 2 and 3 and they have no serious objections for condoning the delay.
3. We are also satisfied with the reasons stated in the affidavit filed in support of the above petitions. Hence, the delay is condoned.
The petitions are ordered.
[M.D., A.C.J.] [S.M., J.] 16.09.2022 Rj https://www.mhc.tn.gov.in/judis