IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 23.04.2025 CORAM :

THE HONOURABLE MR. JUSTICE J. SATHYA NARAYANA PRASAD V.Moorthy .. Petitioner vs 1.The Commissioner Corporation of Chennai Vepery, Chennai - 600 007.

2.The Managing Director Chennai Metropolitan Water Supply and Swerage Board, No.1, Pumping Station Road, Chindadripet, Chennai - 600 002.

3.The Area Officer Chennai Metropolitan Water Supply and Sewerage Board, No.75, Santhome High Road, Pattinampakkam, Santhome, Raja Annamalaipuram, Chennai - 600028.

(R2 and R3 are impleaded as per order dated 29.11.2024 in WMP.No.27141 of 2024) ... Respondents Prayer : Writ Petition is filed under Article 226 of the Constitution of India, praying 1/6

to issue a Writ of Mandamus to consider the petitioner representation dated 20.03.2024 by directing the respondent to act upon the complaints given by the petitioner and to clear the broken and damaged drainage outlet pipes within the time limit issued by this Court.

For Petitioner :

Mr.C.Kanagaraj For Respondents :

Mr.D.B.R.Prabhu, Standing counsel for R1 Mr.K.Vasanthamala for R2 & R3.

O R D E R

This writ petition has been filed to consider the petitioner representation dated 20.03.2024 by directing the respondent to act upon the complaints given by the petitioner and to clear the broken and damaged drainage outlet pipes.

2. Heard the learned counsel for the petitioner and the learned standing counsel for the first respondent and the learned counsel for the respondents 2 and 3 and perused the materials available on record.

3. Pursuant to the orders of this Court dated 21.04.2025, the respondents 2 and 2/6

3 filed the status report, in which it is stated that the inspection was conducted at the premises located at No.8/1, Nattu Muthu Kumarappan Street, Mylapore and the premises situated in a common lane approximately 60 feet from the Greater Chennai Corporation road (Nattu Muthu Kumarappan Street) and in the common lane two houses are located, at present these two houses are using a common /single sewer connection which is in the common lane. It is submitted that the separate sewerage connection was applied by the consumer residing in the above said location and the connection was provided up to the terminal chamber. The consumer is required to construct separate house sewerage pipeline and chambers in this common lane, as it is a private lane. It is further submitted that the respondents provided the separate sewer connection upto the terminal chamber of the common lane, as per the directions of this Court. The aforesaid status report dated 21.04.2025 is taken up on record.

4. In view of the aforesaid factual position, nothing survives for further adjudication in this writ petition. Hence, this writ petition stands closed. No costs. 3/6

23.04.2025 Note : Issue order copy on 28.04.2025 Speaking order / Non-speaking order Index : Yes / No : Yes / No tsh To 1.The Commissioner Corporation of Chennai, Vepery, Chennai - 600 007.

2.The Managing Director Chennai Metropolitan Water Supply and Sewerage Board, No.1, Pumping Station Road, Chindadripet, Chennai - 600 002.

3.The Area Officer Chennai Metropolitan Water Supply and Sewerage Board, No.75, Santhome High Road, Pattinampakkam, Santhome, Raja Annamalaipuram, Chennai - 600028.

4/6

J. SATHYA NARAYANA PRASAD , J.

tsh 5/6

23.04.2025 6/6