Madras High CourtOP/22/2016allowed

S.Divya v. The Union Of India

2016-04-01Honourable The Chief Justice3 pages

In the High Court of Judicature at Madras Dated : 01.04.2016 Coram :

The Hon'ble Mr.Sanjay Kishan Kaul, Chief Justice O.P.No.22 of 2016 S.Divya .. Petitioner -vs1.The Union of India, rep. by the General Manager, Southern Railway, Head Quarters Office, Park Town, Chennai-3.

2.The Divisional Railway Manager, Salem Division, Southern Railway, Salem-636 005.

3.The Senior Divisional Electrical Engineer (TRD), Salem Division, Southern Railway, Salem-636 005.

.. Respondents Petition filed under Sections 11(6) of the Arbitration and Conciliation Act, 1996, to appoint an Arbitrator to arbitrate all the claims and disputes between the petitioner and the respondents arising out of the Agreement No.SA/TR/2012-13/RR/OML/02B dated 18.02.2015.

For Petitioner : Mr.Amalaraj For Respondents : Mr.P.T.Ravikumar * * * * *

O R D E R

The learned counsel for the respondents states that he has obtained instructions vide letter dated 31.03.2016 that the petitioner has submitted the details regarding loading and unloading of guard boxes on 30.03.2016 requiring payment of Rs.89,330/- towards loading and unloading of guard boxes. This is under process for approval of the higher authority and scrutinizing the bills. Necessary payments, it is stated will be arranged.

2. On the Court query, the learned counsel for the respondents states that payments will be made within a maximum period of three weeks from today. The claim should thus be duly settled by the office of the third respondent, as indicated in Court, within the said period of three weeks.

3. In view aforesaid, no dispute remains for reference to arbitration and the petition is accordingly disposed of as infructuous. No costs.

(S.K.K., CJ.) 01.04.2016 bbr Note: Order copy be issued on 05.04.2016.

The Hon'ble Chief Justice bbr O.P.No.22 of 2016 01.04.2016