Madras High CourtA/3389/2024ordered
M/S The Waterbase Limited v. Mr.Reddy Chiranjeevi Proprietor, M/S. Sree Feeds
2024-10-14Honourable Mr Justice G.K. Ilanthiraiyan1 pages
A.No.3389 of 2024 G.K.ILANTHIRAIYAN, J.
This application has been filed by the applicant to extend the time for completion of arbitration proceedings by a period of nine months.
2. The learned counsel appearing for the respondents have no objection to extend the time.
3. However, considering the stage on which the arbitral proceedings are at, this Court is inclined to extend the time for a further period of three (3) months from today. The learned Arbitrator is requested to complete the proceedings and pass an Award within the said period of three (3) months and the respective parties are also directed to co-operate with the learned Arbitrator.
14.10.2024 rts https://www.mhc.tn.gov.in/judis