← Library
Madras High CourtWP/22250/2021closed

S.Kalamani v. The Superintending Engineer

2024-02-09Honourable Mr Justice S.M. Subramaniam5 pages

2024:MHC:6312

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 09-02-2024

CORAM

THE HONOURABLE MR.JUSTICE S.M. SUBRAMANIAM WP No.22250 of 2021 And WMP No.23461 of 2021 1.S.Kalamani 2.S.Pavithra 3.S.Induja .. Petitioners -vs1.The Superintending Engineer, Kovai Distribution Circle/South, 2.The Executive Engineer,

3.The Assistant Engineer, Elachipalayam, .. Respondents Writ Petition is filed under Article 226 of the Constitution of India praying for the issuance of a Writ of Mandamus, directing the respondent Nos.2 and 3 to sanction addition load to the petitioners power loom in application reference No.200032930821323 and do repair works in the existing poles by considering the representation dated 10.08.2021. For Petitioners :

Mr.K.Myilsamy For Respondents :

Ms.Keerthana Shenoi for Mr.L.Jai Venkatesh, Standing Counsel for TANGEDCO.

O R D E R

Ms.Keerthana Shenoi, learned Standing Counsel appearing on behalf of the respondent-TANGEDCO would submit that the petitioners

submitted a representation on 10.08.2021, seeking additional load. The respondent-TANGEDCO considered the same and granted additional load in favour of the petitioners on 30.09.2021.

2. Since the grievances of the writ petitioners have been redressed, no further adjudication needs to be entertained in respect of the grounds raised in the present writ petition.

3. Accordingly, the present writ petition stands closed. However, there shall be no order as to costs. Consequently, the connected miscellaneous petition is also closed.

09-02-2024 Index : Yes/No Internet: Yes/No Speaking order/Non-Speaking order Svn

To 1.The Superintending Engineer, Kovai Distribution Circle/South, 2.The Executive Engineer, 3.The Assistant Engineer, Elachipalayam,

S.M.SUBRAMANIAM, J.

Svn WP 22250 of 2021 09-02-2024