Uma Jayapal v. D.Vijula
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 13.09.2023 CORAM :
THE HON'BLE MR.SANJAY V.GANGAPURWALA, CHIEF JUSTICE AND THE HON'BLE MR.JUSTICE P.D.AUDIKESAVALU Contempt Petition No.2009 of 2023 Uma Jayapal .. Petitioner versus D.Vijula, Commissioner, Corporation of Chennai, Zone 7, Ward 8 Ambattur, Chennai 53 .. Respondent Prayer: Contempt Petition filed to punish the respondent for wilful disobedience of the orders of this Court dated 10.02.2023 in WP No.3988 of 2023.
For the Petitioner :
Mr.A.Kumar For the Respondents :
Mr.A.Arun Babu
ORDER
(Order of the Court was made by The Hon'ble Chief Justice) We have heard Mr.A.Kumar, learned counsel for the petitioner and Mr.A.Arun Babu, learned counsel for the respondent.
2. The learned counsel for the petitioner submits that the order of this Court dated 10.02.2023 has been flouted by the respondent.
3. Learned counsel for the respondent submits that after the order dated 10.02.2023, the respondent communicated to the petitioner on 22.05.2023 about the re-survey. The original respondent No.3 in the writ petition produced documents showing the existence of patta and also some building plans. The same have been sent to the Tahsildar for verification to confirm the genuineness. Once a report is received, depending upon the report, further steps would be taken in accordance with law.
4. In view of the same, the contempt petition is disposed of. (S.V.G., CJ.) (P.D.A., J.) 13.09.2023 Index : yes/no : Yes/No tar
THE HON'BLE CHIEF JUSTICE AND P.D.AUDIKESAVALU, J.
(tar) Cont.P.No.2009 of 2023 13.09.2023