S.Sivakumar v. The District Collector
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 26.06.2025
CORAM
THE HONOURABLE MR. JUSTICE M.SUNDAR and THE HONOURABLE MR. JUSTICE HEMANT CHANDANGOUDAR S. Sivakumar Petitioner vs.
1.
The District Collector Salem District Salem 636 001 The Divisional Engineer Highways Department Construction and Maintenance Salem The Divisional Engineer Highways Department Construction and Maintenance Sankagiri 4.
Chinna Pillai 5.
Papathi Ammal Respondents Writ Petition filed under Article 226 of the Constitution of India praying to issue a writ of mandamus directing the second respondent to consider the petitioner's representation dated 15.04.2025 to take action against the encroachers.
Page Nos.1/6
For petitioner Mr. J. Sudhakaran For RR 1 to 3 Mr. T.K. Saravanan Additional Government Pleader
ORDER
[made by M.SUNDAR, J.] Subject matter of captioned 'writ petition' [hereinafter 'WP' for the sake of brevity] is alleged encroachment in 'S.No.123 at Pennagar, Sitharkoil, Kosavapatti Post, Sankari Taluk, Salem District' (hereinafter 'said land' for the sake of convenience and clarity) Writ petitioner's request for removal of aforereferred alleged encroachment by way of representation dated 15.04.2025 has not yielded results and that has necessitated captioned WP, is the submission of Mr.J.Sudhakaran, learned counsel for writ petitioner. Issue notice to official respondents (RR 1 to 3). Page Nos.2/6
4.
Mr. T.K. Saravanan, learned Additional Government Pleader, accepts notice for RR 1 to 3. Learned State counsel submits that survey of said land will be done within a period of six weeks from today, i.e., on or before 07.08.2025, after putting all concerned, including private respondents on notice, and depending on the outcome of the survey, action for removal of encroachment (if found) will be commenced vide the Tamil Nadu Highways Act, 2001 (Tamil Nadu Act 34 of 2002) as expeditiously as the business of official respondents would permit but in any event within a period of six weeks therefrom, i.e., on or before 18.09.2025. This submission is recorded.
5.
Though obvious, we make it clear that all the rights and contentions of RR 4 and 5 stand preserved and this order does not impinge upon their rights. Therefore, there is no impediment in dispensing with notice to RR 4 and 5 and taking up the captioned WP with the consent of the learned State counsel and learned counsel for writ petitioner. We do so.
Page Nos.3/6
6.
In the light of the narrative thus far, captioned WP is disposed of in the aforesaid manner, recording the stated position of learned State counsel. There shall be no order as to costs. (M.S., J.) (H.C., J.) 26.06.2025 cad Page Nos.4/6
To 1.
The District Collector Salem District Salem 636 001 The Divisional Engineer Highways Department Construction and Maintenance Salem The Divisional Engineer Highways Department Construction and Maintenance Sankagiri Page Nos.5/6
M.SUNDAR, J.
and HEMANT CHANDANGOUDAR, J.
cad 26.06.2025 Page Nos.6/6