M/S.Jsw Renew Energy Limited v. The District Collector
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 19.06.2025
CORAM
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH M/s.JSW Renew Energy Limited Rep. by its Manager, Mr.Siva Sankar L, JSW Centre, Bandra Kurla Complex, Bandra (East), Mumbai- 400 059.
Petitioner Vs The District Collector, Tiruppur District, Tiruppur.
Respondent Writ Petition filed under Article 226 of the Constitution of India seeking issuance of a Writ of Mandamus directing the respondent to consider and pass orders on the petitioner's application dated 04.04.2025 for the issuance of No Objection Certificate/Permission to erect the 33kv electric poles and transmission lines at the extreme boundaries of Stream (Oodai) situated at Sy. Nos. 553/A, 556, 568, 577/B, 579, 581/A, 582, 596, 597, 600/B, 628 and 634/C of Thattaravalasu Village situated within the Erasinampalayam Village Panchayat and at Sy.Nos.721, 722, 723, 731, 739, 741, 758, 759 and 761 of Mulanur Village within the Mulanur Town Panchayat as per G.O. (Ms) No.101, Water Resources (R2) Department, dated 30.09.2024 within a period that may be stipulated by this Court. For Petitioner : Mr.A.Ilaya Perumal For Respondent : Mr.E.Vijay Anand, Additional Government Pleader ***** 1/4
O R D E R
This writ petition has been filed seeking issuance of a writ of mandamus directing the respondent to consider the application submitted by the petitioner on 04.04.2025 wherein the petitioner is seeking for issuance of No Objection Certificate to erect 33kv electric poles and transmission lines in the subject property.
2. Heard Mr.A.Ilaya Perumal, learned counsel for petitioner and Mr.E.Vijay Anand, learned Additional Government Pleader appearing for respondent.
3. The case of the petitioner is that the petitioner is involved in setting up renewable energy project at Tiruppur District in Tamil Nadu. Necessary permission has already been granted by the concerned authorities. The petitioner submitted an application seeking for permission/no objection in order to erect electric police/transmission lines. Since the same is kept pending, the present writ petition has been filed.
4. Taking into consideration the facts and circumstances of the 2/4
case and the materials placed before this Court, there shall be a direction to the respondent to deal with the application submitted by the petitioner and to take a decision within a period of four (4) weeks from the date of receipt of a copy of this order.
This writ petition is disposed of with the above direction. No costs.
19.06.2025 Index: Yes/no Speaking Order/Non-Speaking Order gm To The District Collector, Tiruppur District, Tiruppur.
N.ANAND VENKATESH, J 3/4
gm 19.06.2025 4/4