IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED 17.07.2017

CORAM

THE HONOURABLE DR.JUSTICE ANITA SUMANTH O.P. No.272 of 2010 M/s.Ennore Port Limited, P.T.Lee Chengalvaraya Naicker Maaligai (1 Floor), No.23, Rajaji Salai Chennai - 600 001.

represented by its Director Co-operative A.Rajagopalan .. Petitioner -vs1. M/s. Afcons Infrastructure Limited, No.16, Shah Industrial Estate, Veera Desai Road, Azad Nagar, P.O., Post Box No.11978, Andheri (West), Mumbai - 400 053.

2.S.Sankaramoorthy 3.A.Ananthakrishnan 4.V.G.Koshy .. Respondents Prayer: Original Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 praying to set aside the Award dated 09.12.2006 and order dated 2005 and direct the first respondent to pay the liquidated damages of Rs.5.675 crores together with interest at 18% p.a. from the date 15.12.2000 till the date of payment to the petitioner for the delay in completion of Section 1 of the work and to direct the respondents to pay the costs of the proceedings to the petitioner.

http://www.judis.nic.in

Dr.ANITA SUMANTH,J.

vga For Petitioner : Mr.K.Manoj Menon For Respondents : Mr.D.Balaraman

ORDER

Learned counsel for the parties would bring to the notice of this Court the Settlement Agreement dated 22.08.1997 executed by the parties in terms of which the disputes stand settled. 2.Accordingly, this petition is closed in terms of Settlement Agreement dated 22.08.1997 interse that shall form part and parcel of this order. No order as to costs. Consequently, connected Applications are closed.

17.07.2017 vga O.P. No.272 of 2010 http://www.judis.nic.in