IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 22.11.2023

CORAM

THE HON'BLE MR.SANJAY V.GANGAPURWALA, CHIEF JUSTICE AND THE HON'BLE MR.JUSTICE D.BHARATHA CHAKRAVARTHY Dr.K.Rajasigamani .. Petitioner -vs1. The Union Territory of Puducherry, Rep. by the Chief Secretary, Chief Secretariat Building, Puducherry.

2. The Superintending Engineer, Circle-II, Public Works Department, Puducherry.

3. The Executive Engineer (Irrigation), Public Works Department, Puducherry.

4. K.Rathiga

5. Suganthy .. Respondents Prayer: Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Certiorari calling for the records on the file of the 3rd respondent herein bearing Ref.No. 3760/PW/EEI/DB/C-20/Culvert/ 2018-19 dated 08.03.2019 and quash the same as illegal and invalid since the same is not in accordance with the site condition.

For the Petitioner :

No appearance For the Respondents :

Mr.V.Vasantha Kumar Addl. Govt. Pleader (Puducherry) for RR 1 to 3 :

Mr.K.S.Karthik Raja for RR 4 and 5 * * * * *

ORDER

(Made by the Hon'ble Chief Justice) None appears for the petitioner.

2. We have heard Mr.V.Vasantha Kumar, learned Additional Government Pleader for respondent Nos.1 to 3 and Mr.K.S.Karthik Raj, learned counsel for respondent Nos.4 and 5.

3. The learned Additional Government Pleader submits that the 4th and 5th respondents had applied for permission for construction of RCC culvert across irrigation channel. The third respondent accorded temporary permission on 08.03.2019 to respondent Nos.4 and 5 to construct RCC culvert within a period of six months. The same could

not be constructed. Now, the permission has expired. The application of the 4th and 5th respondents for renewal of permit extending the time is also rejected on 14.12.2022.

In view of the above, nothing survives in the writ petition. The writ petition is dismissed. There will be no order as to costs. (S.V.G., CJ.) (D.B.C., J.) 22.11.2023 Index : Yes/No : Yes/No sra To

1. The Union Territory of Puducherry, Rep. by the Chief Secretary, Chief Secretariat Building, Puducherry.

2. The Superintending Engineer, Circle-II, Public Works Department, Puducherry.

3. The Executive Engineer (Irrigation), Public Works Department, Puducherry.

THE HON'BLE CHIEF JUSTICE AND D.BHARATHA CHAKRAVARTHY, J.

(sra) 22.11.2023