← Library
Madras High CourtA/3691/2022allowed

Bank Of Baroda v. Ganesan Builders Limited

2022-08-29Honourable Mr Justice Senthilkumar Ramamoorthy2 pages

A.No.3691 of 2022 A.No.3691 of 2022 in C.S.(Comm.Div.) No.106 of 2022 SENTHILKUMAR RAMAMOORTHY, J.

The defendant has presented this application to condone the delay of 10 days in filing the written statement. The plaintiff has no objection to this application being allowed. Upon examining the affidavit in support and being satisfied that sufficient cause is shown, this application is allowed. The Registry is directed to receive the written statement. Both parties are directed to file the affidavit of admission / denial in respect of documents filed by the counter party and draft issues.

2. List the matter on 12.09.2022.

29.08.2022 rna https://www.mhc.tn.gov.in/judis 1/2

A.No.3691 of 2022 SENTHILKUMAR RAMAMOORTHY, J.

rna A.No.3691 of 2022 in C.S.(Comm.Div.) No.106 of 2022 29.08.2022 https://www.mhc.tn.gov.in/judis 2/2