THE HONOURABLE MR. JUSTICE K.K.SASIDHARAN Writ Petition No.35069 of 2013 1 N.LAKSHMI NARASIMMAN [ PETITIONER ] Vs 1 THE CHAIRMAN TAMILNADU ELECTRICITY BOARD 144, ANNA SALAI CHENNAI-2 2 THE CHIEF ENGINEER/PERSONNEL TAMILNADU ELECTRICITY BOARD 144, ANNA SALAI CHENNAI-2 3 THE SUPERINTENDING ENGINEER NAGAPATTINAM ELECTRICITY DISTRIBUTION CIRCLE NAGAPATTINAM 4 THE INSPECTOR OF LABOUR KARIMGUDY CHETTY STREET VELIPALAYAM NAGAPATTINAM DISTRICT [ RESPONDENTS ] Petition filed under Article 226 of the Constitution of India for the issuance of writ of Mandamus directing the respondents to regularize the services of the petitioner and consequently appoint the petitioner in the permanent category based on the order of the 4th respondent dated 2.3.1999.
For Petitioner : Mr.M.R.Kuyilan For Respondents : Mrs.R.Varalakshmi for R1 to R3
O R D E R
The petitioner worked as Contract Labourer under the third
respondent in various sub stations. The petitioner submitted an application to the management to regularize his service. Since there was no follow up action taken by respondents 1 to 3, the petitioner along with others approached the fourth respondent. The fourth respondent was pleased to pass an order, directing regularizing the service of thirty employees including the petitioner vide order dated 2.3.1999. It is the case of the petitioner that the said order was challenged by respondents 1 to 3 before this Court in Writ Petition No.17290 of 1999. The Writ Petition was dismissed by this Court by order dated 7.4.2004. According to the petitioner, the order was upheld by the Division Bench.
2. It is the grievance of the petitioner that notwithstanding the earlier order, respondents 1 to 3 have not taken up action to comply with the order passed by the fourth respondent. The petitioner is therefore before this Court.
3. The third respondent is directed to take action to comply with the order passed by the fourth respondent dated 2.3.1999 and pass appropriate orders as expeditiously as possible and in any case within a period of four months from the date of receipt of a copy of this order.
4. The Writ Petition is disposed of with the above direction. No costs.
Sd/- Assistant Registrar //True Copy// Sub Assistant Registrar ajr To 1 THE CHAIRMAN TAMILNADU ELECTRICITY BOARD 144, ANNA SALAI CHENNAI-2 2 THE CHIEF ENGINEER/PERSONNEL TAMILNADU ELECTRICITY BOARD 144, ANNA SALAI CHENNAI-2 3 THE SUPERINTENDING ENGINEER NAGAPATTINAM ELECTRICITY DISTRIBUTION CIRCLE NAGAPATTINAM
4 THE INSPECTOR OF LABOUR KARIMGUDY CHETTY STREET VELIPALAYAM NAGAPATTINAM DISTRICT W.P.No.35069 of 2013 jp(co) pmk.27.2.2015