Madras High CourtCMP/17677/2021ordered

Salem District Central Co-Operative Bank Ltd., v. A.Murugesan,

2022-06-09Honourable Mr. Justice Paresh Upadhyay,Honourable Mrs Justice V.Bhavani Subbaroyan1 pages

C.M.P.No.17677 of 2021 in W.A.SR.No.92763 of 2021 PARESH UPADHYAY, J., and V. BHAVANI SUBBAROYAN, J.

[Order of the Court was made by PARESH UPADHYAY, J.] This is the petition to condone the delay of 232 days in preferring the appeal.

2. Heard the learned advocates for the respective parties.

3. Having heard the learned advocates and having considered the material on record, this Court finds that the delay is properly explained.

Delay is condoned and this petition is allowed.

(P.U., J.) (V.B.S., J.) 09.06.2022 raa/1 https://www.mhc.tn.gov.in/judis