L.Balakrishnan v. The Chairman
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 28.11.2023
CORAM
THE HONOURABLE Ms.JUSTICE R.N.MANJULA W.P. No.22505 of 2021 and W.M.P.Nos.22726 & 22727 of 2021 1.L.Balakrishnan S/o.Lakshmanan 2.M.Manikandan C/o.R.Leelavathi 3.P.Karthikeyan S/o.Palanisamy 4.G.Pongurusamy S/o.Ganesan 5.P.Sathishkumar S/o.P.Palanisamy 6.P.Sukumar S/o.Perumal 7.M.Anbalagan S/o.P.Madhaiyan ... Petitioners /Vs/ 1.The Chairman Tamil Nadu General & Distribution Corporation (TANGEDCO) No.144, Anna Salai Chennai 600 002 1/7
2.The Chief Engineer (Personnel) Tamil Nadu General & Distribution Corporation (TANGEDCO) No.144, Anna Salai Chennai 600 002 3.The Chief Engineer Mettur Thermal Power Station - I Tamil Nadu Electricity Generation and Distribution Corporation Mettur Dam 4.The Superintending Engineer (Operation) Mettur Thermal Power Station Tamil Nadu Electricity Generation and Distribution Corporation Mettur Dam 5.The Joint Director Industrial Safety and Healthy Authority under the Tamil Nadu Industrial Establishment Conferment of Permanent status to workmen Act 1981 Salem ... Respondents Writ Petition is filed under Article 226 of the Constitution of India for issuance of Writ of Certiorarified Mandamus to call for the records relating to the order passed by the third Respondent in Lr.No.169/Adm.II/A4/F.CC/2020 dated 27.02.2020 quash the same and direct the respondents 1 to 4 to confirm the service of the Petitioners as per the order passed by the 5th Respondent in No.A/4600/2011 dated 17.11.2015.
For Petitioner :
Mr.D.Rajkumar For Respondents :
Mr.Anand Gopalan for Mr.T.S.Gopalan & Co 2/7
ORDER
This Writ Petition has been filed for issuance of Writ of Certiorarified Mandamus to call for the records relating to the order passed by the third Respondent in Lr.No.169/Adm.II/A4/F.CC/2020 dated 27.02.2020 quash the same and direct the respondents 1 to 4 to confirm the service of the Petitioners as per the order passed by the 5th Respondent in No.A/4600/2011 dated 17.11.2015.
2.Heard Mr.D.Rajkumar, learned counsel for the Petitioner and Mr.Anand Gopalan, learned counsel for Mr.T.S.Gopalan & Co, learned counsel for the Respondents.
3.When the matter is taken up for hearing today, Mr.Anand Gopalan, learned counsel for the Respondents, relied upon an order passed by this Court in W.P.No.15265 & 15267 of 2021 dated 17.11.2023, wherein in an identical issue this Court by referring an order passed by this Court in W.P.No.2732 of 2020 dated 05.02.2020 held as under:
4.When the matter is taken up for hearing today, 3/7
Ms.V.M.Sreenidhi, for AGAM Legal Associates, learned counsel for the Respondents, relied upon an order passed by this Court in W.P.No.2732 of 2020 dated 05.02.2020, wherein in an identical issue this Court has held as under:
"2.
It is seen from records that the petitioner was working as a Contract Labour and he had given a representation to the 3rd respondent to regularize his service inline with 12 (3) Settlement. The 3rd respondent has rejected the claim made by the petitioner by proceedings dated 26.04.2018. This order has now became a subject matter of challenge before this Court.
3.
Considering the nature of claim that has been made by the petitioner and the reasons assigned by the 3rd respondent for rejecting the same, this Court is not the appropriate authority to decide upon the rejection order passed by the 3rd respondent. The petitioner has to necessarily work out his remedy before the appropriate forum and seek for a substantial relief against the respondents. It would require factual considerations of 12(3) Settlement as well as the period during which the petitioner was engaged as contract labour.
4.
This writ petition is therefore disposed of by giving liberty to the petitioner to work out his remedy before the appropriate forum, in accordance with law.
5.
In view of the facts of circumstances of this case and the order passed passed by this Court in W.P.No.2732 of 2020 dated 05.02.2020, these Writ Petitions are not maintainable."
6.In the result, these Writ Petitions are dismissed with liberty to the Petitioner to work out his remedy before the appropriate forum, in accordance with law. Consequently 4/7
connected Miscellaneous Petitions are closed." 4.In view of the same, this Writ Petition is dismissed with liberty to the Petitioner to work out his remedy before the appropriate forum, in accordance with law. Consequently connected Miscellaneous Petitions are closed. 28.11.2023 Index : Yes/No : Yes/No Speaking Order/Non-Speaking Order sai To 1.The Chairman Tamil Nadu General & Distribution Corporation (TANGEDCO) No.144, Anna Salai, Chennai 600 002 2.The Chief Engineer (Personnel) Tamil Nadu General & Distribution Corporation (TANGEDCO) No.144, Anna Salai, Chennai 600 002 3.The Chief Engineer Mettur Thermal Power Station - I Tamil Nadu Electricity Generation and Distribution Corporation Mettur Dam 4.The Superintending Engineer (Operation) Mettur Thermal Power Station Tamil Nadu Electricity Generation and Distribution Corporation Mettur Dam 5/7
5.The Joint Director Industrial Safety and Healthy Authority under the Tamil Nadu Industrial Establishment Conferment of Permanent status to workmen Act 1981 Salem 6/7
R.N.MANJULA, J.
sai W.P. No.22505 of 2021 and W.M.P.Nos.22726 & 22727 of 2021 28.11.2023 7/7