Rinki Maheswari v. The Superintending Engineer
1/5
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 01-07-2025
CORAM
THE HONOURABLE MR JUSTICE N. ANAND VENKATESH Ms.Rinki Maheswari Petitioner(s) Vs
1. The Superintending Engineer CEDC, Central- TANGEDCO 110 KV Valluvarkottam SS Complex, MGR Salai, Chennai- 600 034.
2.The Executive Engineer TANGEDCO, O & M Mylapore.
3.The Assistant Executive Engineer TANGEDCO O & M, Central CIT Nagar, CIT Nagar, Chennai- 600 004.
Respondent(s) PRAYER Writ Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Mandamus, directing the 2nd respondent to forthwith
2/5 provide domestic electricity service connection to the petitioner's premises at Flat no.2B, Second Floor, 'Sakthi Krishna', C.I.T. Colony 1st Main Road, Mylapore, Chennai- 600 004, in pursuance of the order passed by the CGRF dated 18.11.2024.
For Petitioner(s):
Ms.H.Lucia Priyadarshini For Respondent:
Mr.L.Jai Venkatesh Standing Counsel for R1 to R3
ORDER
This writ petition has been filed for issue of writ of mandamus directing the 2nd respondent to provide domestic electricity service connection to the premises belonging to the petitioner based on the order passed by CGRF dated 18.11.2024.
2.When the matter was taken up for hearing today, the learned Standing Counsel produced the written instructions recieved from the Assistant Engineer. It is seen that pursuant to the order passed by the CGRF dated 18.11.2024, legal opinion has been sought for and that the application submitted by the petitioner is under process.
3/5 3.Taking into consideration the facts and circumstances of the case and the written instructions submitted before this Court, there shall be a direction to the petitioner to submit a fresh application before the Assistant Engineer (O & M), Alwarpet, Chennai and on receipt of the same, the Assistant Engineer shall process the application in line with the order that has been passed by CGRF dated 18.11.2024 and do the needful, within a period of four weeks from the date of receipt of the fresh application submitted by the petitioner. 4.This writ petition is disposed of with the above directions. No Costs. 01-07-2025 Index:Yes/No Speaking/Non-speaking order Internet:Yes ssr
4/5 To
1. The Superintending Engineer CEDC, Central- TANGEDCO 110 KV Valluvarkottam SS Complex, MGR Salai, Chennai- 600 034.
2.The Executive Engineer TANGEDCO, O & M Mylapore.
3.The Assistant Executive Engineer TANGEDCO O & M, Central CIT Nagar, CIT Nagar, Chennai- 600 004.
5/5 N.ANAND VENKATESH J.
ssr 01-07-2025