Jaheer Hussian v. The District Collector
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 06.08.2024
CORAM
THE HONOURABLE MR. JUSTICE S.SOUNTHAR W.P No.21836 of 2024 Jaheer Hussain
...Petitioner
Vs.
1.The District Collector Permabalur, First Floor Master Plan Complex Perambalur Collector Office Road Sungu Pettai, Perambalur 621 212.
2.The Thasildar Revenue Department Office Kunnam Taluk, Perambalur District.
3.The Inspector of Town Suvey Revenue Department Office Kunnam, Perambalur District.
...Respondents
Prayer: Writ Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Mandamus, directing the respondents 2 & 3 to allot a surveyor and survey the property situated at Survey Nos.22/29B, 29/40, 29/41, 29/42, 30/11, 30/6, 30/7, 32/2, 32/3, 32/4, 32/5, Pennakonam North Village, 1/5
Kunnam Taluk, Perambalur District in pursuant to the payment made by the petitioner vide petition Form bearing No.2024/0123/16/000310 dated 29.02.2024 within the time that may be fixed by this Court. For Petitioner : Ms.D.Kamatchi For Respondents : Mr.A.Selvendran for R1 to R3 Special Government Pleader
O R D E R
The petitioner herein seeks a direction to the respondents 2 & 3 to allot a Surveyor and survey the property situated in S.Nos.22/29B, 29/40, 29/41, 29/42, 30/11, 30/6, 30/7, 32/2, 32/3, 32/4, 32/5, Pennakonam North Village, Kunnam Taluk, Perambalur District, pursuant to the payment made by the petitioner vide petition Form bearing No.2024/0123/16/000310 dated 29.02.2024 within the time that may be fixed by this Court.
2. According to the petitioner, he got the above mentioned land by a settlement deed executed by her mother dated 07.02.2024 and he has been in possession and enjoyment of the same. The petitioner submitted an application to the respondents 2 & 3 seeking survey of the above mentioned land and he 2/5
also paid necessary charges for surveying the property as seen from the online acknowledgment issued to the petitioner dated 29.02.2024, which is enclosed in page No.49 of the typed set of papers.
3. The learned Special Government Pleader appearing for the respondents would submit that the survey of the property will be completed within a period fixed by this Court.
4. In view of the limited prayer made by the petitioner, without expressing any opinion on the merits of the claim made by the petitioner, this Court is inclined to issue a direction to the respondents 2 & 3 to complete the survey of the petitioner's land within a period of 8 weeks from the date of receipt of copy of this order.
5. With the above direction, this Writ Petition is disposed of. No costs.
06.08.2024 Index : Yes/No Internet : Yes/No Speaking Order/Non-Speaking Order dna 3/5
To 1.The District Collector Permabalur, First Floor Master Plan Complex Perambalur Collector Office Road Sungu Pettai, Perambalur 621 212.
2.The Thasildar Revenue Department Office Kunnam Taluk, Perambalur District.
3.The Inspector of Town Suvey Revenue Department Office Kunnam, Perambalur District.
4/5
S.SOUNTHAR , J.
dna W.P No.21836 of 2024 06.08.2024 5/5