M/S.Sri Venkateshwara Spinning Mills P Ltd., v. Tamil Nadu Electricity Regulatory Commission
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 31.07.2023
CORAM
MR.JUSTICE N.SESHASAYEE and W.M.P.No.21976 of 2023 M/s.SriVenkateshwara Spinning Mills P. Ltd., HTSC No.039094390412 S.F.No.201/1, 201/4, 201/5, Muthur Road Veemampalayam Post, Kangayam, Tirupur 630701 Repdby its Authorized Signatory S.Rameshkumar ... Petitioner Vs.
1.Tamil Nadu Electricity Regulatory, Commission Repd. by its Secretary, 19-A, Rukmini Lakshmipathy Salai, (Marshall's Road) Egmore, Chennai-600 008.
2.The Chairman, Tamil Nadu Generation and Distribution, Corporation Limited, 144, Anna Salai, Chennai-600 002.
3.The Director Finance Tamil Nadu Generation and Distribution Corporation Limited, 144, Anna Salai Chennai-600 002.
1/4
4.The Superintending Engineer, TANGEDCO, Palladam Electricity Distribution Circle, PALLADAM ... Respondents PRAYER: The writ petition filed under Article 226 of the Constitution of India, to issue a writ of Mandamus, forbearing the respondent and their men, agents from collecting current consumption charges, demand charges and any arrears from the petitioner bearing HTSC No.039094390412 until the respondent makes payment of the outstanding dues of Rs.13,63,519/- (for the year of 2022-2023) payable to the petitioner or give adjustment in the current consumption charges payable by the petitioner till the entire amount is adjusted. For Petitioner : Mr.R.S.Pandiyaraj For Respondents : Mr.L.Jaivenkatesh Standing Counsel for TNEB
ORDER
By consent, this writ petition is taken up for final disposal at the admission stage itself.
2.The petitioner is a captive generator, and it has sold the surplus electricity it has generated to the TANGEDCO. In this regard, the TANGEDCO owes the petitioner a sum of Rs.13,63,519/- for the year 2022 to 2023. The necessary 2/4
particulars of petitioner's claim are provided and acknowledged by the 3rd respondent vide its communication, a copy of which is made available in the typed set of papers.
3.Mr.L.Jaivenkatesh, the Standing Counsel has taken notice for TNEB, the respondents herein.
4.There is a claim and a counter claim on either side. Inasmuch as the respondent / TANGEDCO has admitted the purchase of electricity from the petitioner and also a liability of Rs.1363,519/-, it is only appropriate that the said sum is adjusted against any of its claim against the outstanding from its end to the petitioner. Till the accounts on either side is entirely reconciled, the respondent / TANGEDCO is prohibited from taking any coercive steps to realize its dues from the petitioner.
5.This writ petition is disposed of with the above directions. No Costs. Consequently, the connected miscellaneous petition is closed. 31.07.2023 (1/3) kas Index : Yes / No 3/4
N.SESHASAYEE, J.
kas To 1.Tamil Nadu Electricity Regulatory, Commission Repd. by its Secretary, 19-A, Rukmini Lakshmipathy Salai, (Marshall's Road) Egmore, Chennai-600 008.
2.The Chairman, Tamil Nadu Generation and Distribution, Corporation Limited, 144, Anna Salai, Chennai-600 002.
3.The Director Finance Tamil Nadu Generation and Distribution Corporation Limited, 144, Anna Salai Chennai-600 002.
4.The Superintending Engineer, TANGEDCO, Palladam Electricity Distribution Circle, PALLADAM and W.M.P.No.21976 of 2023 31.07.2023 (1/3) 4/4