These applications are presented for purposes of extending the mandate of the arbitral tribunal. The applicant is the claimant before the arbitral tribunal. The contesting parties submit that the arbitral proceedings are at the stage of final arguments.

2. By taking note of the current stage of the arbitral proceedings, the time for conclusion of such proceedings by pronouncing an award is extended by a period of six months from the date of receipt of a copy of this order.

28.09.2022 rna 1/2 https://www.mhc.tn.gov.in/judis

A.Nos.4167, 4168, 4170 of 2022 SENTHILKUMAR RAMAMOORTHY, J.

rna A.Nos.4167, 4168, 4170 of 2022 28.09.2022 2/2 https://www.mhc.tn.gov.in/judis