S.Sridharan, v. The Principal Secretary To Government,
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 30.11.2022
CORAM
THE HONOURABLE MR.JUSTICE S.M.SUBRAMANIAM S.Sridharan
...Petitioner
Vs.
1.The Principal Secretary to Government, Public Works (A1) Department, Fort St.George, Chennai - 9.
2.The Engineer-in-Chief & Chief Engineer, Public Works Department, Chepauk, Chennai - 5.
3.The Executive Engineer, Public Works Department, Environment Division, Madurai - 625 002.
..Respondents Prayer : Writ Petition filed Under Article 226 of the Constitution of India, to issue a Writ of Mandamus, directing the respondents to consider the claim of the petitioner for awarding selection grade in the cadre of Asst Engineer for having rendered 10 years of service from 06.05.1993 to 06.07.2004 and revise the scale of pay and grant him all consequential service and monetary benefits based on the proposal sent by the Executive 1/4
Engineer, Public Works Department, WRO, Madurai in his letter No.PA1/316/ 2015 dated 02.07.2015 within a reasonable time. For Petitioner : Mr.K.Venkat Ramani Senior Counsel For Mr.M.Muthappan For Respondents : Mr.R.P.Murugan Raja Government Advocate
ORDER
The learned Senior counsel appearing on behalf of the writ petitioner made a submission that the grievances of the writ petitioner were redressed. Thus, no further adjudication is required.
2. Recording the above said submission made by the learned Senior counsel for the writ petitioner, the writ petition stands closed. No costs. 30.11.2022 Index : Yes Speaking order :Yes kak 2/4
To 1.The Principal Secretary to Government, Public Works (A1) Department, Fort St.George, Chennai - 9.
2.The Engineer-in-Chief & Chief Engineer, Public Works Department, Chepauk, Chennai - 5.
3.The Executive Engineer, Public Works Department, Environment Division, Madurai - 625 002.
3/4
S.M.SUBRAMANIAM, J.
kak 30.11.2022 4/4