R.Karthikeyan, v. The Engineer In Chief,
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED 17.11.2016
CORAM
THE HON'BLE MR.JUSTICE M.S.RAMESH W.P.No.28837 of 2012 and M.P.No.1 of 2012 1.R.Karthikeyan 2.P.Dhandayuthapani 3.K.Vadivel 4.P.Velumani 5.M.Murugan 6.G.Subramani 7.C. Elumalai 8.M.Mayilsamy 9.A.Tambi 10.V.Ranjithkumar 11.S.Vijayakumar 12.R.Rajendran 13.P.Pachaiappan 14.M.S.Prabhu 15.S.Srinivasan 16.R.Duraisamy 17.S.Sivakumar 18.K.Madhu 19.R.Ravikumar 20.S.Thangaraj 21.A.Sekar 22.R.Balasubramanian 23.A.Sakthivel (This writ petition is dismissed as withdrawn as against the petitioner Nos.5 to 9,13 to 17, 21 and 22 vide in WMP.No.21751 of 2016 dated 17.11.2016) .. Petitioners Vs 1.The Engineer in Chief Public Works Department, Chepauk, Chennai 600 005.
2.The Chief Engineer, Public Works Department, W.R.O., Trichy Region, Trichy-20.
3.The Superintending Engineer, Melkaveri Basin Circle, Salem-7.
4.The Executive Engineer, Mettur Dam Division, Mettur Dam-1. .. Respondents Prayer: Writ petition filed under Article 226 of the Constitution of India praying for issuance of a writ of Mandamus directing the first and second respondent to pass appropriate orders regularizing the service of the petitioners taking into consideration the initial date of entry not service and in accordance to rules and consequently grant all attendant and monetary benefits within a stipulated time.
For Petitioners : Mr.Malarvizhi Udayakumar For R1 to R4 : Mr.R.Govindasamy Spl.Govt.Pleader
O R D E R
Though the petitioners 1 to 4, 10 to 12, 18 to 20 and 23 have sought for a larger relief as against the respondents 1 and 2 to pass orders regularizing their services, taking into consideration the initial date of entry into service, the learned counsel appearing for the petitioners 1 to 4, 10 to 12, 18 to 20 and 23 would submit that if a direction is given to the first respondent to consider the representation dated 09.11.2009 made by the Tamil Nadu Government Officials Union on behalf of the petitioners, they would be satisfied.
2. In view of the limited prayer sought for in the writ petition, there shall be a direction to the first respondent to consider the representation of the Tamil Nadu Government Officials Union on behalf of the petitioners 1 to 4, 10 to 12, 18 to 20 and 23 dated 09.11.2009 on its own merits and pass orders in accordance with law, within a period of four weeks from the date of receipt of a copy of this order. With the above direction, this writ petition is disposed of. No costs. Consequently, connected miscellaneous petition is closed.
Sd/- Asst.Registrar (CS VI ) /true copy/ Sub Asst. Registrar kkd
To 1.The Engineer in Chief Public Works Department, Chepauk, Chennai 600 005.
2.The Chief Engineer, Public Works Department, W.R.O., Trichy Region, Trichy-20.
3.The Superintending Engineer, Melkaveri Basin Circle, Salem-7.
4.The Executive Engineer, Mettur Dam Division, Mettur Dam-1.
1 cc to M/s. Malarvizhi udayakumar, Advocate, Sr. 66493 (11/1/16) W.P.No.28837 of 2012 and M.P.No.1 of 2012 SK (CO) kk 10/1