IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 01.09.2025

CORAM:

THE HONOURABLE MR. JUSTICE D.BHARATHA CHAKRAVARTHY Muniyan ... Petitioner Vs 1.

Mr.Karthikeyan, Assistant Engineer (O & M), TANGEDCO, Kaveripattinam, Krishnagiri District.

Mr.Saravanan, Inspector of Police, Kaveripattinam Police Station, Krishnagiri District.

... Respondents Prayer: Contempt Petition filed under Section 11 of Contempt of Courts Act, 1971, to punish the respondents herein for non compliance and wilful disobedience of the order of this Court made in W.P.No.5767 of 2025 dated 19.02.2025.

For Petitioner : M/s.C.Prabakaran For Respondents : Mr.R.Madhusudhanan for R1 : Mr.S.Subbiah Government Advocate (Crl Side) for R2 1/4

ORDER

The contempt petition has been filed complaining willful disobedience of the Order passed by this Court in W.P.No.10441 of 2025 dated 21.03.2025. When the matter came up for hearing, learned Government Advocate (Crl.side) as well as the learned Counsel for the TANGEDCO would submit that the line has since been drawn with due protection of the police. It is now come to light that the traget that is fixed for effecting free connection stands now exhausted and if only further connections are ordered to be released, then one of the connections can be given to the petitioner. 3.

That may be so, the application was made in the year 2006 and the writ petition itself was filed only because there was third party objection. But for the objection, the connection would have been effected at the relevant point of time.

4.

In that view of the matter, even though target would have been fixed, considering the fact that such a defense was not taken in the main writ petition, the Authorities are directed to effect the connection within a period of four (4) weeks from the date of uploading of web copy of this order without waiting for the certified copy.

5.

Post the matter for reporting compliance on 06.10.2025. 2/4

01.09.2025 veda To 1.

Assistant Engineer (O & M), TANGEDCO, Kaveripattinam, Krishnagiri District.

Inspector of Police, Kaveripattinam Police Station, Krishnagiri District.

D.BHARATHA CHAKRAVARTHY, J.

3/4

veda 01.09.2025 4/4