Madras High CourtA/4299/2024ordered
M/S.Rpn Engineers Chennai Private Limited v. The Union Of India Rep By The General Manager And Another
2024-10-03Honourable Mr Justice G.K. Ilanthiraiyan1 pages
A. No.4299 of 2024 G.K. ILANTHIRAIYAN. J., This application has been filed, seeking to extend the time period for completing the arbitration proceedings in Arb.F.No.5 of 2022 before the Tribunal and passing of an award arising out of an arbitration agreement No.50/DY.CE/CN/I/MAS/2021 dated 01.04.2021 between the applicant and the respondents for a period of 6 months.
2. Heard both sides.
3. Considering the submissions made on both sides, time is extended by three months for completing the arbitration proceedings. Accordingly, this application is ordered.
03.10.2024 ab https://www.mhc.tn.gov.in/judis