The Divisional Engineer v. Pachaiyappan
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 13.08.2025
CORAM
THE HONOURABLE MRS JUSTICE R. KALAIMATHI in C.M.P.Nos.5525, 5527 and 5533 of 2025 in S.A.Sr.No.30283, 30166 and 30135 of 2025 C.M.P.No.16463 of 2025
1. The Divisional Engineer,
2. The Assistant Engineer, ..Petitioners Vs.
1. Pachaiyappan
2. Sampath
3. Arumugam
4. Chitra ..Respondents C.M.P.No.16468 of 2025
1. The Divisional Engineer,
2. The Assistant Engineer, ..Petitioners
Vs.
1. Pachiyappan
2. Sampath
3. Thavamani
4. Chellammal ..Respondents C.M.P.No.16470 of 2025
1. The Divisional Engineer,
2. The Assistant Engineer, ..Petitioners Vs.
1. Pachaiyappan
2. Sampath
3. Gajavalli
4. Minor Thaivanai
5. Minor Kruthika Minor respondents 4 and 5 represented by next friend/ Guardian/mother first respondent Gajavalli ..Respondents Prayer in C.M.P.No.16463 of 2025: This Civil Miscellaneous Petition is filed under Section 148 of C.P.C., to extend the time granted to comply with the order dated 28.04.2025 made in C.M.P.No.5525 of 2025 in S.A.Sr.No.30283 of 2025 to deposit in E.P.No.4 of 2023 in O.S.No.29 of 2022 on the file of Sub Court, Chengam for a further period of three weeks. Prayer in C.M.P.No.16468 of 2025: This Civil Miscellaneous Petition is filed
under Section 148 of C.P.C., to extend the time granted to comply with the order dated 28.04.2025 made in C.M.P.No.5527 of 2025 in S.A.Sr.No.30166 of 2025 to deposit in E.P.No.10 of 2023 in O.S.No.27 of 2022 on the file of Sub Court, Chengam for a further period of three weeks. Prayer in C.M.P.No.16470 of 2025:- This Civil Miscellaneous Petition is filed under Section 148 of C.P.C., to extend the time granted to comply with the order dated 28.04.2025 made in C.M.P.No.5523 of 2025 in S.A.Sr.No.30135 of 2025 to deposit in E.P.No.11 of 2023 in O.S.No.28 of 2022 on the file of Sub Court, Chengam for a further period of three weeks. For Petitioner(s) in all C.M.Ps : Mr.R.Ramanlaal Additional Advocate General assisted by Mr.T.Arunkumar Additional Government Pleader COMMON ORDER The learned counsel for the petitioners would submit that G.O.(Ms) No.125 has been passed on 29.07.2025 and seeks short time to comply with the order passed by this Court dated 28.04.2025.
2. In consideration of the above said details, time for depositing the amount of Rs.5,00,000/- each (totally a sum of Rs.15,00,000/-) is extended till 28.08.2025. Accordingly, these Civil Miscellaneous Petitions are ordered.
R. KALAIMATHI, J.
mac
3. List the matter on 04.09.2025 for compliance report. 13.08.2025 mac To
1. The Additional District Court at Thiruvannamalai
2. The Subordinate Court, Chengam
3. The Divisional Engineer,
4. The Assistant Engineer,
5. The Public Prosecutor, High Court, Madras.
6. The Section Officer, VR Section, Madras High Court.
in C.M.P.Nos.5525, 5527 and 5533 of 2025 in S.A.Sr.No.30283, 30166 and 30135 of 2025