The Special Tahsildar (La) v. Kannudurai
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 27-02-2026
CORAM
THE HON'BLE MR.JUSTICE P.B. BALAJI AS No. 313 of 2026 and CMP.No.5780 of 2026 The Special Tahsildar (LA) Unit II Arasu Cements Factory, Ariyalur.
..Appellant(s) Vs.
1. Kannudurai S/o.(Late) Samydurai.
2. Managing Director Arasu Cements Corporation, Anna Salai, Chennai
3. Deputy General Manager Arasu Cements Factory, Ariyalur ..Respondent(s) PRAYER : Appeal Suit filed under Section 54 of the Land Acquisition Act, 1894, to set aside the decree passed in LAOP No. 107 of 2003 dated 26.04.2022 on the file of the Sub Court, Ariyalur.
For Appellant :
Mr.M.Murali, Govt. Advocate For Respondents :
Mr.R.Gokulakrishnan [R1] Mr.A.Sivaji [R2 & R3]
JUDGMENT
Challenging the enhancement of compensation from Rs.1200/- to Rs.1500/- per cent, the present appeal suit has been filed.
2. Heard Mr.M.Murali,, learned Government Advocate appearing for the appellant, Mr.R.Gokulakrishnan, learned counsel for the first respondent and Mr.A.Sivaji, learned counsel for respondents 2 & 3.
3. The Government Advocate appearing for the appellant would state that originally, the compensation of Rs.250/- per cent was awarded by the Land Acquisition Officer. However, on reference, the Reference Court enhanced the compensation to Rs.1200/- per cent. As against the same, appeals were preferred before this Court and the same were allowed and the compensation was reduced to Rs.900/- per cent. In the meantime, the order fixing the compensation, at Rs.900/- has been set aside and therefore, pending the appeal proceedings, the Board has passed the resolution and uniformly fixed a sum of Rs.1500/- per cent, as the compensation to all the land owners.
4. Mr.M.Murali, learned Government Advocate appearing for the appellant would also bring to my notice that in the connected appeals in A.S.Nos.432 of 2020 and etc., batch dated 02.02.2026 as well as in A.S.Nos.238
of 2020 and etc., batch dated 05.09.2025, the Board has come forward to pay a compensation of Rs.1500/- per cent with statutory benefits to all affected land owners under the scheme has been taken note of and the appeals have been disposed of.
5. Mr.R.Gokulakrishnan, learned counsel for first respondent would fairly submit that he has no objection for the appeals being disposed of on the same lines in which the earlier appeals have been disposed of fixing the compensation at Rs.1500/- per cent.
6. In the light of the above, the appeal suit is disposed of fixing the compensation amount for the acquired lands at Rs.1500/-per cent with no deduction towards development charges. The award passed by the Reference Court is modified by enhancing the amount from Rs.1200/- to Rs.1500/- per cent. It is needless to state that the statutory benefits under Section 23(1-A), 23(2) and 28 of the Land Acquisition Act are to be calculated on the enhanced amount. Mr.M.Murali, learned Government Advocate brings to my notice that compensation amount has already been deposited and therefore, there is no requirement to give any direction for deposit of any further amount.
P.B.BALAJI, J.
gsk The land owners/respondent are permitted to withdraw the same by taking out a formal application. No costs. Connected miscellaneous petition is closed. 27-02-2026 Index: Yes/No Speaking/Non-speaking order GSK To
1. The Sub Court, Ariyalur
2. Managing Director Arasu Cements Corporation, Anna Salai, Chennai
3. Deputy General Manager Arasu Cements Factory, Ariyalur AS No. 313 of 2026 and CMP.No.5780 of 2026