A.No.4394 of 2022 SENTHILKUMAR RAMAMOORTHY, J The claimant before the arbitral tribunal seeks an extension of the mandate of the arbitral tribunal.

2. Learned counsel for the applicant invited by attention to the Minutes of the proceedings held on 04.08.2022.

3. Both parties state that the matter is at the stage of final arguments. They seek extension by six months.

4. By taking into account the stage of arbitral proceedings, the mandate of the arbitral proceedings is extended by a period of six months from the date of receipt of a copy of this order. 29.09.2022 kal 1/2 https://www.mhc.tn.gov.in/judis

SENTHILKUMAR RAMAMOORTHY,J kal A.No.4394 of 2022 29.09.2022 2/2 https://www.mhc.tn.gov.in/judis