← Library
Madras High CourtCONT P/2646/2024closed

S.M.Murugappan, v. Rajesh Kanna And Another

2024-09-27Honourable Mr Justice N. Anand Venkatesh4 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 27.09.2024

CORAM

THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH S.M.Murugappan .. Petitioner Vs.

1.M.Rajesh Kanna, The Assistant Executive Engineer (O&M), Tamilnadu General and Distribution Corporation Ltd., (Urapakkam East Section), Chengalpattu Electricity Distribution Circle, Guduvancherry.

2.D.Sabithadevi .. Respondents Prayer: Contempt Petition filed under section 11 of the Contempt of Courts Act, 1971, to punish the 1st respondent for the willful disobedience of the order of this Court dated 31.08.2021 made in W.P.No.18035 of 2021.

For Petitioner :

Mr.G.Vasudevan For R1 :

Mr.L.Jai Venkatesh Standing Counsel for TANGEDCO 1/4

O R D E R

The Contempt Petition has been filed to punish the 1st respondent for willful disobedience of the order of this Court in W.P.No.18035 of 2021 dated 31.08.2021.

2.When the matter was taken up for hearing, the learned Standing Counsel appearing on behalf of the 1st respondent produced the proceedings of the Assistant Executive Engineer dated 10.05.2024. The Assistant Executive Engineer has come to a conclusion that the genuineness of the documents produced by both the sides cannot be decided by the 1st respondent. He has to workout the remedy before the concerned Authority / Court.

3.The decision taken by the 1st respondent cannot be faulted, since, the 1st respondent cannot decide on the genuineness of the documents. Therefore, the petitioner has to necessarily give a complaint in this regard either to the District Registrar or must workout the remedy before the Civil Court. Based on the final decision, the 1st respondent will act upon the same.

2/4

4.Recording the above, this Contempt Petition stands closed. 27.09.2024 krk Index : Yes / No Internet : Yes / No : Yes / No 3/4

N.ANAND VENKATESH, J.

krk 27.09.2024 4/4