Madras High CourtA/4248/2024ordered
Unicon Engineers v. The General Manager
2024-10-24Honourable Mr Justice G.K. Ilanthiraiyan1 pages
A.No.4248 of 2024 G.K.ILANTHIRAIYAN, J.
This application has been filed by the applicant to extend the further period of Nine months to enable the Arbitrational Tribunal to pass Award in I.A.F.No.8/2021/MHCAC.
2. Considering the stage on which the arbitral proceedings are at, this Court is inclined to extend the time for a further period of Nine (9) months from today. The learned Arbitrator is requested to complete the proceedings and pass an Award within the said period of Nine (9) months and the respective parties are also directed to co-operate with the learned Arbitrator.
24.10.2024 vm https://www.mhc.tn.gov.in/judis