Madras High CourtWP/28870/2019disposed of

M.Y.Gulmuhamed v. Senior Executive Engineer

2021-12-07Honourable Mr Justice M.Dhandapani3 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 07.12.2021

CORAM

THE HONOURABLE MR.JUSTICE M.DHANDAPANI W.P.NO.28870 OF 2019 M.Y.Gul Mohammed

...Petitioner

vs.

1.The Senior Executive Engineer, Metrourban, TNEB, Tatabad, Coimbatore.

2.The Executive Engineer, Pem Nagar, TNEB, Tatabad, Coimbatore.

3.The Assistant Executive Engineer, TNEB, K.K.Puthur, Saibaba Colony, Coimbatore - 641 038.

4.M.Y.Nazeer Ahmed 5.M.Y.Sheik Ahmed 6.M.Y.Mohammed Shafee

...Respondents

Writ Petition filed under Article 226 of the Constitution of India praying for the issuance of a Writ of Mandamus, directing the Respondents 1 to 3 to consider the representation dated 04.09.2019 and effect electricity service connection for consumer No.030220052816, phase-3 Meter No.8096718 in the premises at Survey No.319/4, Part situate in Sangawar Village, Coimbatore Taluk, Coimbatore District.

For Petitioner :

Ms.Shobana Ramasubramanian For Respondents 1 to 3 :

Mr.L.Jai Venkatesh For Respondents 4 to 6 :

No appearance

O R D E R

Petitioner has come up with this Writ Petition seeking a direction to the Respondents 1 to 3 to consider his representation dated 04.09.2019 and effect electricity service connection for consumer No.030220052816, phase-3 Meter No.8096718 in his premises at Survey No.319/4, Part situate in Sangawar Village, Coimbatore Taluk, Coimbatore District. 2.

According to the Petitioner, he is the absolute and lawful owner of the property measuring an extent of 1320 sq. ft. comprised in Survey No.319/4 part, situated in Sangawar Village, Coimbatore Taluk, Coimbatore District and he developed the same into a Car garage to cater to the automobile/mechanic needs of the locality. On 04.09.2019, he applied to the 1st Respondent to provide electricity service connection to his property. As no action was taken on his representation, the Petitioner is before this Court.

3.

Heard the learned counsel on either side and perused the material documents available on record.

4.

Considering the facts and circumstances of the case and without going into its merits, this Court directs the 1st Respondent herein to consider the Petitioner's representation dated 04.09.2019 seeking electricity service connection to his property, and pass appropriate orders in accordance with law, within a period of six weeks from the date of receipt of a copy of this order.

The Writ Petition is disposed of accordingly. No costs. Sd/- Assistant Registrar(CO) // True Copy // Sub Assistant Registrar (aeb) To:

1.The Senior Executive Engineer, Metrourban, TNEB, Tatabad, Coimbatore.

2.The Executive Engineer, Pem Nagar, TNEB, Tatabad, Coimbatore.

3.The Assistant Executive Engineer, TNEB, K.K.Puthur, Saibaba Colony, Coimbatore - 641 038.