Madras High CourtCOMP.A/515/2022delay condoned
Bharat Electricals Limited., Rep.By Its General Manager, Mr.G.Loyola Pedro Vianney, v. The Official Liquidator
2022-12-09Honourable Mr Justice Krishnan Ramasamy1 pages
Comp.A.No.515 of 2022 in C.P.No.280 of 2014 KRISHNAN RAMASAMY, J.
The above application is filed to condone the delay of 1357 days in filing the proof of debt before the Respondent against Company under liquidation M/s Emas Engineers and Contractors Private Limited.
2. This Court is convinced with the reasons stated in the affidavit filed in support of this application and accordingly the delay is condoned as prayed for.
The learned Official Liquidator is permitted to carry out the proceedings if it is otherwise in order and disburse the amount subject to the availability of funds.
09.12.2022 shr https://www.mhc.tn.gov.in/judis 1/1