P.Vaiyapuri, v. The Chief Engineer,
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 09.11.2016
CORAM
THE HONOURABLE MR. JUSTICE R.SUBBIAH Writ Petition No.39182 of 2016 P.Vaiyapuri ... Petitioner vs.
1 The Chief Engineer National Highways Highways office Buildings HRS Campus Sardar Patel Road Chennai-600 025. 2 The Sueprintendent Engineer National Highways Salem.
3 The Divisional Engineer National Highways Coimbatore-641 018.
.. Respondents Writ petition has been filed under Article 226 of the Constitution of India, praying for a Writ of mandamus directing the first respondent to consider and pass orders on the representation made by the petitioner herein on 8.7.2016 which was duly acknowledged by the respondents herein. For Petitioner :
Mr.V.Balaji For Respondents :
Mr.S.N.Parthasarathy, Govt. Advocate
ORDER
By consent, the main writ petition itself is taken up for final disposal.
2. The petitioner has come up with the present writ petition for a mandamus, directing the first respondent to consider and pass orders on his representation dated 8.7.2016.
3. It is the case of the petitioner that he was appointed as Assistant Engineer in Highways Engineering Service by transfer of service and his service was duly regularized in consultation with the Tamil Nadu Public Service Commission. Subsequently, he was promoted as Assistant Divisional Engineer and held the post till his retirement i.e., on 31.1.2015. While so, he came to know that one E.Rathinasamy, who is junior to him, is drawing more pay than the petitioner. In G.O.Ms.No.234 Finance (Pay Cell) Department dated 1.6.2009, detailed guidelines have been given as to the rectification of anomaly of junior getting more pay than senior. Therefore, he sent a representation to the first respondent on 8.7.2016 to re-fix his salary on par with the said E.Rathinasamy, as per G.O.Ms.No.234 Finance (Pay Cell) Department dated 1.6.2009. Since the same was not considered so far, left with no other alternative, the petitioner has come up with the present writ petition for the relief set out earlier.
4. I have heard the learned counsel appearing for the petitioner and the learned Government Advocate, who has taken notice on behalf of the respondents.
5. Considering the facts and circumstances of the case and considering the submissions made on either side, without going into the merits of the claim projected by the petitioner, this Court directs the first respondent to consider the representation of the petitioner dated 8.7.2016 seeking refixation of his salary on par with one E.Rathinasamy and pass appropriate orders, on merits and in accordance with law and also as per G.O.Ms.No.234 Finance (Pay Cell) Department dated 1.6.2009, within a period of six weeks from the date of receipt of a copy of this order. The writ petition is disposed of accordingly. No costs.
Sd/- Assistant Registrar(CO) //True Copy// Sub Assistant Registrar R.SUBBIAH, J sbi
To 1 The Chief Engineer National Highways Highways office Buildings HRS Campus Sardar Patel Road Chennai-600 025.
2 The Sueprintendent Engineer National Highways Salem.
3 The Divisional Engineer National Highways Coimbatore-641 018.
+1cc to Mr.V. Balaji, Advocate, S.R.No.64073 +1cc to the Government Pleader, S.R.No.64626 ev(CO) md(29/11/2016) W.P.No.39182 of 2016