Public Works M/S.Rajsriya Automotive Industries Private Limited v. The Chairman
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 27.09.2023
CORAM
MR.JUSTICE N.SESHASAYEE M/s.Rajsriya Automotive Industries Pvt. Ltd.
Rep. by its AGM - HR & Admin & Authorized Signatory K.Shankar Ground Floor, 95, Harrington Road, Chetpet Chennai 600 031 ... Petitioner Vs.
1.The Chairman Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) 144, Anna Salai Chennai 600 002 2.Director - Finance Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) 144, Anna Salai Chennai 600 002 3.Chief Financial Controller - Revenue Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) 144, Anna Salai Chennai 600 002 1/5
4.The Superintending Engineer TANGEDCO Tirupur Electricity Distribution Circle Tirupur 641664 5.The Superintending Engineer TANGEDCO Theni Electricity Distribution Circle Theni 625531 6.The Superintending Engineer TANGEDCO Krishnagiri Electricity Distribution Circle Krishnagiri 635001 7.The Tamil Nadu Electricity Regulatory Commission 4th Floor, SIDCO Corporate Office Building Guindy, Chennai 600 032 ... Respondents PRAYER: The writ petition filed under Article 226 of the Constitution of India, to issue a Writ of Mandamus, directing the 3rd respondent herein to consider the representation of the petitioner dated 19.08.2023 within a stipulated time. For Petitioner : Mr.S.Satish For Respondents : Mr.L.Jaivenkatesh Standing Counsel - TANGEDCO
ORDER
The petitioner is a wind energy generator and it is now seeking a direction to the respondents to pay for the energy which it has generated and banked with 2/5
TANGEDCO, for the year 2012 to 2013. The petitioner has earlier instituted W.P.No.9319 of 2017 for the purpose and this Court vide its order dated 18.04.2017, had given a direction to the TANGEDCO to pass a speaking order. At the end of the day, the petitioner complains that it is yet to receive payment for the energy that was banked with and utilized by TANGEDCO some six years ago.
2.Heard Mr.L.Jaivenkatesh, the learned standing counsel appearing for the TANGEDCO. The learned counsel submitted that a proposal has already been forwarded by the 3rd respondent to the 4th respondent and a copy was also given to the petitioner.
3.This Court now directs the 4th respondent to disburse the amount due and payable to the petitioner within a period of twelve (12) weeks from the date of receipt of a copy of this order.
4.This writ petition stands disposed of accordingly. No costs. 27.09.2023 kas 3/5
To 1.The Chairman Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) 144, Anna Salai Chennai 600 002 2.Director - Finance Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) 144, Anna Salai Chennai 600 002 3.Chief Financial Controller - Revenue Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) 144, Anna Salai, Chennai 600 002 4.The Superintending Engineer TANGEDCO Tirupur Electricity Distribution Circle Tirupur 641664 5.The Superintending Engineer TANGEDCO Theni Electricity Distribution Circle Theni 625531 6.The Superintending Engineer TANGEDCO Krishnagiri Electricity Distribution Circle Krishnagiri 635001 7.The Tamil Nadu Electricity Regulatory Commission 4th Floor, SIDCO Corporate Office Building Guindy, Chennai 600 032 4/5
N.SESHASAYEE, J.
kas 27.09.2023 5/5