M/S.Edac Engineering Ltd v. M/S.G.R.Infrastructure Pvt Ltd
O.S.A.No. 291 of 2019
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 11.06.2025 CORAM :
THE HONOURABLE DR.JUSTICE ANITA SUMANTH and THE HONOURABLE MR.JUSTICE N.SENTHILKUMAR O.S.A.No. 291 of 2019 M/s. EDAC Engineering Ltd., Formerly SPIC Jel Engineering Construction Limited, Rep. by Mr.S.Muthamizselvan its Authorised Signatory, Presently Mr.Balaji Pathak, Legal Officer, SPIC House, 3rd Floor, New No.88, Mount Road, Chennai - 600 032.
.. Appellant vs M/s. G.R.Infrastructure Pvt Ltd., HO 202, Poonam Chambers 'A' Wing, AB Road, Worli, Mumbai - 400 018 Rep. by its Authorised Signatory, Mr.Kiran A.Gujarathi .. Respondent Prayer : Appeal filed under Order XXXVI Rule 11 read with Clause 15 of Letters Patent against judgment and decree dated 10.07.2019 made in Application No. 2521/2018 in C.S.No. 812/2016. 1/2 https://www.mhc.tn.gov.in/judis
O.S.A.No. 291 of 2019 DR. ANITA SUMANTH, J.
and N.SENTHILKUMAR, J.
For Appellant :
Mr.M.Aravind Subramanian, Senior Counsel for Mr.Mohd Sajid For Respondents :
Mr.C.Thiagarajan
JUDGMENT
(Delivered by Dr. ANITA SUMANTH.,J) Read this order in continuation of and in conjunction with order dated 23.04.2025.
2. Though mediation has failed in this matter, lis has subsequently been settled inter se the parties.
3.
Recording the same, this Original Side Appeal is closed as settled as an endorsement is made by both learned counsel on record for both parties to this effect. No costs.
[A.S.M., J] [N.S., J] 11.06.2025 Index:Yes/No ssm To The Sub Assistant Registrar, Original Side, High Court, Madras.
O.S.A.No. 291 of 2019 2/2 https://www.mhc.tn.gov.in/judis