S.Anil Kumar v. The Chief Engineer
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 11.11.2019
CORAM
THE HONOURABLE MR.JUSTICE M.DHANDAPANI W.P.No.30669 of 2019 And W.M.P.Nos.30744 and 30745 of 2019 S.Anil Kumar ... Petitioner Vs.
1.The Chief Engineer/ Personnel 144, Annasalai, Chennai - 2.
2.The Superintendent Engineer, Purchase and Administration, Mettur Thermal Power Station - II, Mettur - 636 406.
3.The Superintendent Engineer, Villupuram Electricity Distribution Circle, Villupuram - 605 602, Villupuram Dt.
4.The Executive Engineer/ Operation and Maintenance, Villupuram Electricity Distribution Circle, Kandamangalam - 605 102 Villupuram Dt.
5.The Assistant Executive Engineer/ Operation and Maintenance, Villupuram Electricity Distribution Circle, Kandamangalam - 605 102, Villupuram Dt.
6.The Superintending Engineer, Thirumakkottai Gas Turbine Power Station, Mannagrudi, Thiruvarur Dt.
... Respondents
Prayer:
Petition filed under Article 226 of the Constitution of India to issue a Writ of Certiorarified Mandamus to call for records relating to the relieving order of the 5th respondent by its Memo.No.AEE/O&M/ KMG/CI/F.RWE/D.NO.75/2019 dated :
03.07.2019 consequent to the relieving order 1st respondent has issued transfer order by its Memo No.041953/627/G42/G421/2019-1 dated 26.08.2019 and quash the same and further direct the 1st respondent to retain the petitioner at Kandamangalam Division in Villupuram Electricity Distribution Circle and further direct the 3rd respondent to disburse the salary from 03.07.2019 to till date in view of the petitioner's representation dated 27.09.2019.
For Petitioner : Mr.S.Arivazhagan For Respondents : Mr.Fakkir Mohideen
O R D E R
The learned counsel appearing for the petitioner submits that the petitioner has been retained in the Villupuram region and has also made an endorsement to that effect in the petition. 2.In view of the above, the relief sought for in the writ petition becomes infructuous. Hence, this writ petition is dismissed as infructuous. The petitioner is entitled to receive salary and the salary has to be paid within a period of four weeks from the date of receipt of a copy of this order. No costs. Consequently, the connected miscellaneous petition is closed.
Sd/- Assistant Registrar(CS-VI) // True Copy// Sub Assistant Registrar pri To 1.The Chief Engineer/ Personnel 144, Annasalai, Chennai - 2.
2.The Superintendent Engineer, Purchase and Administration, Mettur Thermal Power Station - II, Mettur - 636 406.
3.The Superintendent Engineer, Villupuram Electricity Distribution Circle, Villupuram - 605 602, Villupuram Dt.
4.The Executive Engineer/ Operation and Maintenance, Villupuram Electricity Distribution Circle, Kandamangalam - 605 102 Villupuram Dt.
5.The Assistant Executive Engineer/ Operation and Maintenance, Villupuram Electricity Distribution Circle, Kandamangalam - 605 102, Villupuram Dt.
6.The Superintending Engineer, Thirumakkottai Gas Turbine Power Station, Mannagrudi, Thiruvarur Dt.
+1cc to Mr.M.Fakkir Mohideen, Advocate, SR.No.93694. +1cc to Mr.S.Arivazhagan, Advocate, SR.No.93906. W.P.No.30669 of 2019 And W.M.P.Nos.30744 and 30745 of 2019 KK (CO) CSR(19/12/2019)