Indus Towers Limited v. Union Bank Of India
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 07.11.2023 CORAM :
THE HON'BLE MR.SANJAY V.GANGAPURWALA, CHIEF JUSTICE AND THE HON'BLE MR.JUSTICE D.BHARATHA CHAKRAVARTHY Indus Towers Limited Rep. by its authorised signatory S.Prasanna Espee IT Park, NP 5 5th Floor, Jawaharlal Nehru Road Ekkatuthangal, Chennai 600 032.
..
Petitioner Vs.
1. Union Bank of India Asset Recovery Branch Rep. by its Chief Manager & Authorised Officer Bimal Sukumar Post Box No.8 No.235, Oppanakara Street Coimbatore 641 001.
2. O.K.Sivasubramanian
3. R.Bavani
4. Rajagopal ..
Respondents [R3 & R4 impleaded vide order dated 16.10.2023]
Prayer: Petition filed under Article 226 of the Constitution of India seeking a writ of Certiorarified Mandamus calling for the records of the 1st respondent vide their letter reference No.ARBCBE/MISC/5/2023-24 dated 22.09.2023 and quash the same and consequently, direct the 1st respondent or its successors, representatives including any auction purchaser to provide 24/7 access without disturbing any activities related to the Cell Phone Tower situated at Balaji Kripa Kalayanamandapam.
For the Petitioner : Mr.P.J.Rishikesh For the Respondents : Mr.Sriram for Respondent-1
ORDER
(Made by the Hon'ble Chief Justice) We have heard Mr.P.J.Rishikesh, learned counsel for the petitioner and Mr.Sriram, learned counsel for the first respondent.
2. The petitioner is a tenant of the property owned by the mortgagor to the bank. The mortgagor had mortgaged the said property to the bank. The bank exercised its right under the Securitisation and Reconstruction of Financial Assets and Enforcement
of Security Interest Act, 2002 and sold the said property.
3. Learned counsel for the petitioner submits that if four months time is given, the petitioner would vacate the premises and remove its belongings.
4. Today, none appears for the respondents 3 and 4, though served. The respondents 3 and 4 are the auction purchasers.
5. Considering the fact that the petitioner was doing business in the said premises and it has its belongings, we grant two months' time to the petitioner to remove its belongings and hand over vacant possession to the respondents.
6. On lapse of two months, if the petitioner does not vacate the premises and remove its belongings, then, it would be open to the respondents to take physical possession of the property in accordance with law.
7. The writ petition is disposed of. There will be no order as to costs. Consequently, W.M.P.Nos.28298, 28299, 28301 and 28304 of 2023 are closed.
(S.V.G., CJ.) (D.B.C., J.) 07.11.2023 Index :
Yes/No :
Yes/No kpl To The Chief Manager & Authorised Officer Bimal Sukumar Union Bank of India Asset Recovery Branch Post Box No.8 No.235, Oppanakara Street Coimbatore 641 001.
THE HON'BLE CHIEF JUSTICE AND D.BHARATHA CHAKRAVARTHY, J (kpl) 07.11.2023