IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 15.11.2019

CORAM:

THE HONOURABLE DR.JUSTICE G.JAYACHANDRAN WRIT PETITION NO.29694 OF 2019 AND W.M.P.NO.29590 OF 2019 M.Pratap Arumugam .. Petitioner /versus/

1. The Superintending Engineer, TNEB, Kamarajar Nagar Colony, Ammapet (PO)-636 014. Salem By pass Road, Tamil Nadu-636 014

2. The Additional Assistant Engineer, TNEB Power House, Mallur-636 203.

3. The Assistant Engineer, TNEB, Junior Engineer Office, Panamarathu Patti Nagar, Salem-636 204.

4. Power Grid Corporation of India Ltd., Tharamangalam Road, K.R.Thoppur, Salem District-636 013.

.. Respondents Prayer:Writ Petition is filed under Article 226 of the Constitution of India, to issue a Writ of Certiorarified Mandamus, to call for the records of the 3rd respondent pertaining to the order No.AE/O&M/T/PMP/F.DOC/D.080/2019-2020, dated 03.07.2019 and quash the same and consequently direct the 4th respondent to issue NOC to the petitioner as per law and consequently direct the respondents to issue the approval to the petitioner for the temporary/permanent electrical connection as sought for by the petitioner in his application dated 22.05.2019. For petitioner : Mr.R.Jagadeesan For Respondents : Mr.S.K.Rameshwar St.c for R1 to R3 Mr.Kalyanaraman for M/s.Aiyar & Dolia for R4

O R D E R

The grievance of the petitioner herein is that the tower and electrical line erected by the Power Grid Corporation Ltd. is running across his land. Therefore, when he sought for https://hcservices.ecourts.gov.in/hcservices/

electricity connection from TANGEDCO, they asked for NOC from the Power Grid Corporation Limited. The said communication of the TANGEDCO is under challenge in this writ petition.

2. Instead of keeping this writ petition pending, it is suffice to direct the petitioner to approach the Power Grid Corporation Limited with all the relevant documents for getting NOC. On receipt of the request of the petitioner for issuing NOC, the Power Grid Corporation Limited shall pass appropriate orders in accordance with law within a period of two weeks from the date of representation of the petitioner. If the Power Grid Corporation Limited issued NOC, the same shall be considered by the TANGEDCO for providing service connection to the petitioner herein within a period of four weeks.

3. With the above observation, this writ petition is disposed of. Consequently, the connected miscellaneous petition is closed. No costs.

Sd/- Assistant Registrar(CS I) //True Copy// Sub Assistant Registrar rpl To

1. The Superintending Engineer, TNEB, Kamarajar Nagar Colony, Ammapet (PO)-636 014.

Salem By pass Road, Tamil Nadu-636 014

2. The Additional Assistant Engineer, TNEB Power House, Mallur-636 203.

3. The Assistant Engineer, TNEB, Junior Engineer Office, Panamarathu Patti Nagar, Salem-636 204.

+1cc to Mr.K.V.Subramanian, Advocate, S.R.No.95159 +1cc to M/s.Aiyar & Dolia, Advocate, S.R.No.95928 W.P.No.29694 of 2019 and W.M.P.No.29590 of 2019 PA(CO) CS/17/12/2019 https://hcservices.ecourts.gov.in/hcservices/