M/S. Gannon Dunkerly And Co Ltd., v. Bharat Heavy Electricals Limited
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 21.08.2025
CORAM
THE HONOURABLE MR JUSTICE ABDUL QUDDHOSE A.No.4140 of 2025 M/s.Gannon Dunkerly and Co.
.. Applicant vs Bharat Heavy Electricals Limited .. Respondent For applicant :
Mr.K.Gowthamkumar For respondent :
Mr.K.Harishankar
ORDER
This application has been filed under Section 29A of the Arbitration and Conciliation Act seeking extension of time for the Arbitrator to pronounce an arbitral award.
2.Learned counsel for the respondent has stated no objection for allowing this application.
1/2 https://www.mhc.tn.gov.in/judis
ABDUL QUDDHOSE,J.
vga 3.This Court is satisfied with the reasons stated in the affidavit filed in support of this application since sufficient cause has been shown by the applicant for seeking extension of time.
4.Accordingly, this application is allowed as prayed for by granting extension of time for the Arbitrator to pronounce the Arbitral Award by another period of six months until 03.03.2026.
21.08.2025 vga A.No.4140 of 2025 2/2 https://www.mhc.tn.gov.in/judis