M/S.P And C Projects Pvt Ltd v. Dr.J.Radhakrishnan Ias., And Another
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 01.02.2024
CORAM
THE HONOURABLE MR.JUSTICE C.SARAVANAN Cont.P.Nos.2576, 2577, 2888, 2581, 2890, 2889, 2580, 2578, 2579 & 2891 of 2023 and Cont.P.Nos.58 & 59 of 2024 Cont.P.No.2576 of 2023:
M/s.P&C Projects Private Limited, Represented by its Director.
... Petitioner Vs
1. Dr.J.Radhakrishanan, I.A.S., Additional Chief Secretary/Commissioner Greater Chennai Corporation, Ripon Building, Chennai - 600 003.
2. Thiru.Vijayakumar, Superintending Engineer, Storm Water Drain Department, Greater Chennai Corporation, Ripon Building, Chennai - 600 003.
... Respondents Prayer: Petition filed under Section 11 of Contempt of Courts Act, to punish the Respondent for wilful disobedience of the order of this Court dated 02.09.2022 in W.P.No.13357 of 2020.
1/3
For Petitioner : Mr.V.P.Sengottuvel learned Senior Counsel for A.Akshay For Respondents : Mr.Pramod Kumar Senior Standing Counsel for Mrs.P.T.Ramadevi Standing Counsel COMMON ORDER There is an apparent compliance of the Court order by the respondents. However, the respondents have rejected the request of the petitioner for reimbursement of the GST payable on account of the change in the regime from VAT to GST with effect from 01.07.2017.
2. Considering the fact that the scope of enquiry in contempt petition is limited, these contempt petitions are closed with liberty to the petitioner to challenge the order in accordance with law. 01.02.2024 Index: Yes/ No rgm 2/3
C. SARAVANAN, J.
rgm Cont.P.Nos.2576, 2577, 2888, 2581, 2890, 2889, 2580, 2578, 2579 & 2891 of 2023 and Cont.P.Nos.58 & 59 of 2024 01.02.2024 3/3