Madras High CourtA/8588/2019ordered

M/S.Premco Rail Engineers Ltd. Axis Multi Complex, Cf-9, 4rd Floor, v. Kamarajar Port Limited(Erstwhile Ennore Port Limited)

2019-11-25Honourable Mrs Justice Pushpa Sathyanarayana2 pages

A.No.8588 of 2019 in O.P.No.124 of 2018 PUSHPA SATHYANARAYANA, J.

This application is filed by the applicant seeking to extend the time for a period of four months with effect from 17.11.2019 to enable the Arbitral Tribunal to pass the award.

2.

This Court, vide order dated 18.04.2018 in O.P.No.124 of 2018, had appointed Mr.S.Balachandran, Retd. CEE/NFR, as Sole Arbitrator to adjudicate upon the disputes between the petitioner and the respondent. It is stated that arguments were completed and reserved for passing of orders. As the mandate of the tribunal has expired on 17.11.2019, the parties have prayed for extension of time for conclusion of arbitration proceedings. 3.

Heard both sides.

http://www.judis.nic.in

PUSHPA SATHYANARAYANA.J vsm 4.

With the consent of both learned counsel, time is extended by three months from the date of receipt of a copy of this order for completion of the Arbitral proceedings and for passing the award. The parties are directed to co-operate with the Arbitrator for passing of the order as expeditiously as possible.

5.

Accordingly, this application stands ordered. 25.11.2019 vsm Note: Issue order copy by Next week.